Why did Quang Tri adjust the project of leveling the ground and essential infrastructure at La Lay international border gate?

Báo Giao thôngBáo Giao thông29/07/2024


On July 29, the Management Board of Quang Tri Economic Zone announced that it had just issued a decision approving the task of surveying, designing and estimating the investment preparation for the step of preparing a feasibility study report to adjust and supplement the project of Leveling the ground and essential technical infrastructure in the central area of La Lay international border gate, Quang Tri province (phase 2).

Vì sao Quảng Trị điều chỉnh dự án san nền, hạ tầng thiết yếu tại cửa khẩu quốc tế La Lay?- Ảnh 1.

La Lay international border gate in A Ngo commune, Dakrong district, Quang Tri province.

The scope of the survey includes items that need to be adjusted and supplemented according to the Resolution recently approved by the People's Council of Quang Tri province at the meeting on July 11, 2024.

According to the Resolution on adjusting the project investment policy that has just been approved, the scale of adjustment and supplementation includes: Adjusting the scale of leveling the width of the exit waiting area from 35m down to 16m - 29m depending on the location. For the route connecting the entry waiting area with the main traffic route, adjusting and cutting the asphalt concrete road surface structure 11m wide according to the approved documents; complete the investment according to the planning (35m wide) with concrete structure.

In addition, the project of completing the import waiting area (within 100m of the border) and the area for inspection and customs clearance of imported goods will be added.

The investment scale is to complete the structure with cement concrete with an area of about 3.15 hectares. Of which, the import waiting area (outside 100m of the border) is about 1.9 hectares; the entrance gate, inspection area, and customs clearance of imported goods is about 1.25 hectares.

Invest in building a drainage system with a length of about 355m and other auxiliary items.

The total investment after adjustment is 163 billion VND, an increase of 55 billion VND due to the addition of items to complete the import waiting area (outside 100m of the border) and the area for inspection and customs clearance of imported goods.

Vì sao Quảng Trị điều chỉnh dự án san nền, hạ tầng thiết yếu tại cửa khẩu quốc tế La Lay?- Ảnh 2.

A corner of La Lay international border gate from Laos to Vietnam.

Vì sao Quảng Trị điều chỉnh dự án san nền, hạ tầng thiết yếu tại cửa khẩu quốc tế La Lay?- Ảnh 3.

A corner of La Lay international border gate on National Highway 15D, Quang Tri province. (Photo taken in April 2023)

The structure of additional investment capital includes capital from the land clearance project to implement the project to upgrade and expand National Highway 9 from National Highway 1 to Cua Viet Port of 35 billion VND and revenue from auctioning land use rights in Lao Bao Special Economic - Commercial Zone of 20 billion VND. Project implementation progress is from 2021 - 2025.

Previously, the project of Leveling the ground and essential technical infrastructure in the central area of La Lay international border gate, Quang Tri province - phase 2 (A Ngo commune, Dakrong district, Quang Tri province) was approved by the People's Council of Quang Tri province with a total investment of 108 billion VND, with the Quang Tri Economic Zone Management Board as the investor. The project implementation period is from 2021 to 2024.

According to the People's Committee of Quang Tri province, in the past, due to difficulties in investment capital, the infrastructure at La Lay border gate has not been invested synchronously. In particular, the current import waiting area has not been fully invested, so there is no place to arrange vehicles to unload and clear customs through the border gate.

Every day, vehicles have to queue up along Highway 15D to the border gate. At peak times, trucks, tractor-trailers, and container trucks queue up for more than 2km. Meanwhile, Highway 15D is very narrow, with only 2 lanes, many sharp turns, steep slopes, etc. This long queue of vehicles also causes traffic jams, making it difficult to regulate traffic at the border gate area.

Therefore, to reduce procedures and quickly resolve urgent issues at the border gate area, adjusting some project items to suit the actual situation and adding items to complete the entry waiting area (outside 100m of the border) to the project is really necessary...



Source: https://www.baogiaothong.vn/vi-sao-quang-tri-dieu-chinh-du-an-san-nen-ha-tang-thiet-yeu-tai-cua-khau-quoc-te-la-lay-192240729121307022.htm

Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product