According to Mr. Nguyen Van Luu - Director of Khe Bo Hydropower Plant (located in Tam Quang Commune, Nghe An ), by 12:00 on July 23, the flood in Khe Bo Hydropower Reservoir reached its peak with a flow of more than 7,402 m3 /s. Because this hydropower plant is not capable of cutting floods, the plant was forced to discharge water through the project at the same time with a flow of more than 7,402 m3 /s, the sluice gates were fully opened.
"This is a historic flood, the first time Khe Bo hydropower reservoir has had to release floodwaters with such a large flow. The release of floodwaters has also caused flooding downstream. But the hydropower plant cannot help but release," said Mr. Luu.
Source: https://baonghean.vn/xem-lai-thuy-dien-khe-bo-xa-lu-lon-chua-tung-thay-10303002.html