Close-up of Rach Mieu 2 Bridge across Tien River connecting Dong Thap and Vinh Long

The Rach Mieu 2 Bridge construction investment project has a total investment of 6,810 billion VND, expected to be put into operation and use on August 19, 5 months ahead of the Prime Minister's direction.

Báo Công an Nhân dânBáo Công an Nhân dân07/08/2025

Close-up of Rach Mieu 2 Bridge across Tien River connecting Dong Thap and Vinh Long -0
The Rach Mieu 2 Bridge construction investment project is invested by My Thuan Project Management Board ( Ministry of Construction ), with a total investment of 6,810 billion VND from the state budget. The project started in March 2022 and is expected to be completed in August 2025.
Close-up of Rach Mieu 2 Bridge across Tien River connecting Dong Thap and Vinh Long -0
This is a key transport project, connecting provinces and contributing to promoting socio -economic development in the Mekong Delta region.
Close-up of Rach Mieu 2 Bridge across Tien River connecting Dong Thap and Vinh Long -1
The starting point of the project connects to Dong Tam Intersection in Chau Thanh District, Tien Giang Province (now Long Hung Commune, Dong Thap Province) and the end point is about Km16+660 National Highway 60, about 0.71 km from the northern abutment of Ham Luong Bridge in Ben Tre City, Ben Tre Province (now Ben Tre Ward, Vinh Long Province).
Close-up of Rach Mieu 2 Bridge across Tien River connecting Dong Thap and Vinh Long -0
The project has a total length of 17.6 km, including 7.95 km passing through Tien Giang province (now Dong Thap province) and 9.65 km passing through Ben Tre province (now Vinh Long province).
Close-up of Rach Mieu 2 Bridge across Tien River connecting Dong Thap and Vinh Long -2
The project includes 6 construction packages, the road section has a total length of 14.26 km, including 6 bridges on the main route, total length of 3,337.94 m.
Close-up of Rach Mieu 2 Bridge across Tien River connecting Dong Thap and Vinh Long -0
Up to now, the project has handed over 17.6/17.6 km, reaching 100% of the entire route.
Close-up of Rach Mieu 2 Bridge across Tien River connecting Dong Thap and Vinh Long -1
On July 29, the joint venture of contractors constructing the main cable-stayed bridge organized a load test of Rach Mieu 2 Bridge.
Close-up of Rach Mieu 2 Bridge across Tien River connecting Dong Thap and Vinh Long -0
Up to now, the total output value is 3,269/3,284 billion VND, reaching 99.55% of the contract value, faster than planned.

Source: https://cand.com.vn/Giao-thong/can-canh-cau-rach-mieu-2-bac-qua-song-tien-noi-lien-dong-thap-va-vinh-long-i777262/


Comment (0)

No data
No data
Southeast Asian newspapers comment on the resounding victory of the Vietnamese women's team
Wild beauty on Ha Lang grass hill - Cao Bang
Vietnam Air Force practices preparing for A80
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product