The Government will submit a report on the high-speed railway project to the National Assembly before October 21.

Việt NamViệt Nam07/10/2024


Illustration photo

After listening to the Ministry of Transport report on the content of the North-South high-speed railway investment project and the implementation status of railway projects connecting with China, and the opinions of the comrades attending the meeting, the Government Standing Committee concluded as follows:

1. The Politburo and the Party Central Committee have agreed on the investment policy for the construction of the high-speed railway line on the North-South axis with a design speed of 350km/h, transporting passengers, meeting the dual-use requirements for national defense and security, and being able to transport goods when necessary. This is a particularly important project for the country's development, contributing to raising the country's position and foundation in the new era, so it requires the Ministries and branches to be highly determined, make great efforts, and take drastic actions to implement it.

The announcement of the conclusion of the Politburo and the Resolution of the Party Central Committee are two very important political documents, requiring ministries, branches and localities to seriously and effectively implement them; the implementation process needs to be organized effectively to create high unity of awareness in the political system and consensus in society; it is necessary to innovate the way of thinking and doing with the viewpoint: "act decisively, with focus and key points; clearly assign people, progress, time, results and products; mobilize all resources, in which the human resource factor is decisive, mobilize the entire political system to participate; do while learning from experience, gradually expand; do not be hasty, do not be perfectionist; with the spirit of only discussing, not backtracking; preparation work must be strict and thorough but implementation must be fast and effective";

2. Over the past time, the Ministry of Transport has made efforts and determination to prepare the Project well to report to the Politburo and the Party Central Committee, and at the same time focused on preparing and completing the Investment Project Document according to regulations to submit to the State Appraisal Council. The Ministry of Planning and Investment and the State Appraisal Council have been very determined and resolute in organizing the appraisal with the spirit of close, effective and most urgent coordination. The Government Standing Committee commended the Ministry of Transport and highly appreciated the determination and resoluteness of the Ministry of Planning and Investment and the State Appraisal Council; requested ministries, agencies and the State Appraisal Council to continue to promote this spirit in the coming time, striving to complete the appraisal work as soon as possible to submit to the Government and the National Assembly for consideration and approval of the policy before the opening of the 8th session of the 15th National Assembly under the direction of the Party Central Committee and the Politburo.

3. The Government Standing Committee requests the Ministry of Transport to be determined, make efforts, mobilize experienced, dedicated, responsible staff, and focus more on continuing to complete the Dossier, including studying and absorbing as much as possible the opinions of ministries, branches, the Government Standing Committee and the opinions of the State Appraisal Council. For the contents that are not accepted, they must be fully and closely explained to convince the State Appraisal Council and competent authorities to approve. Some contents to note are as follows:

a) Regarding the technical design plan: It is required to closely follow the investment plan for the entire route with a design speed of 350km/h approved by the Politburo and the Central Executive Committee of the Party to calculate and design suitable, feasible and effective technical plans:

– Regarding the route direction, it is necessary to study the most direct route possible to reduce costs, ensure exploitation speed, create new development space, save costs; avoid residential areas and large urban areas but must have a suitable connection plan; convenient for the shortest connection to airports and large seaports; ensure convenient connection to the East-West corridor and connection with railway lines of China, Laos, and Cambodia.

– For stations, it is necessary to calculate and determine a large enough area, ensuring a long-term strategic vision to develop full and modern services, effectively exploiting land resources and new development space.

b) Regarding function: The Politburo has agreed on the function of passenger transport, meeting the dual-use requirements for national defense and security and being able to transport goods when necessary; combining economics and national defense and security. The Ministry of Transport coordinates with the Ministry of National Defense in the design process of the next step to ensure national defense and security requirements.

For the existing North-South railway line, upgrade it to transport goods, tourism and passengers over suitable distances.

c) Regarding the preliminary total investment: carefully review the investment rate that is most suitable to the natural, economic and social conditions of the country and the specific factors of the project to calculate the preliminary total investment capital as accurately as possible, reliably and convincingly; limit the excess of the total investment capital due to subjective factors when approving the investment project and avoid capital increase when implementing investment and construction of the project...

d) Regarding specific and special mechanisms and policies: it is necessary to review and supplement necessary specific mechanisms and policies to mobilize maximum resources and reduce and shorten investment procedures for the Project; supplement the recommendation for the National Assembly to allow: "for mechanisms and policies arising after the National Assembly approves the project investment policy, in cases where policies arise during the implementation process under the authority of the National Assembly, the National Assembly Standing Committee decides and in cases under the authority of the National Assembly Standing Committee, the Government decides; the agencies report to the National Assembly and the National Assembly Standing Committee at the nearest session".

d) Regarding decentralization and delegation of power: The Ministry of Transport closely follows the direction of the Politburo on decentralization and delegation of power to ministries, branches and localities to mobilize resources of the entire political system, contributions of ministries, branches and localities, especially in site clearance, mobilizing resources to implement projects and build stops and parking stations, assigning the Government to develop policies and mechanisms to attract investment resources.

e) Resource mobilization: mobilize diverse resources, in which public investment is the main source (including central and local budgets, loans, issuance of construction bonds, other legal capital sources of the State, etc.), BOT and BT investment capital sources (exchanging land for infrastructure, especially stations and parking lots) and mobilize from other legal capital sources outside the State through specific and special mechanisms, etc.

g) Human resources: ensure the principle of mobilizing the entire political system, people and businesses to participate in implementing the Project.

– The Ministry of Transport will study the establishment of a specialized working group led by a Deputy Minister to develop the Project, mobilizing experts, cadres, civil servants and public employees with capacity and experience, and considering appropriate remuneration policies according to the specific nature of the Project.

– The Ministry of Transport reviews and, if necessary, adds a Deputy Minister in charge of implementing the Project. The Ministry of Transport shall report to the Prime Minister to report to the competent authority for consideration and decision.

– Ministries, branches, Vietnam Railway Corporation and relevant agencies review human resources to have training and supplementary plans to serve the project implementation and operation process.

h) Regarding procedures: it is necessary to study a mechanism to shorten the time; quickly carry out implementation procedures, and spend time focusing on construction.

i) Regarding impact assessment and investment efficiency assessment: coordinate with the Ministry of Finance to review and evaluate macroeconomic indicators (public debt, foreign debt, etc.); the assessment of project economic efficiency needs to be comprehensive and comprehensive; determine that project implementation will help enhance the country's potential and position; help reduce people's travel costs, reduce logistics costs, increase competitiveness, facilitate people's travel, increase land value, etc.

k) Regarding construction materials: there must be a specific mechanism for land exploitation, common construction materials and decentralization, with maximum authority for localities to handle licensing and environmental impact assessment.

l) Regarding site clearance, conversion of forest use purposes and rice land use purposes: it is necessary to review and decentralize to localities to have a mechanism to proactively implement the conversion of forest use purposes and rice land use purposes in case of adjustments to the scope and area due to changes, adjustments to the route and location of project works. The project has been approved for investment policy, localities will implement it, and the inspection will be carried out by post-inspection method.

4. About progress:

a) The Ministry of Transport shall promptly collect comments and complete the dossier to send to the Ministry of Planning and Investment and the State Appraisal Council before October 10, 2024. The Ministry of Transport shall closely coordinate with the State Appraisal Council to promptly collect and explain comments.

b) The State Appraisal Council shall complete the appraisal before October 18, 2024;

c) The Government's Submission must be sent to the National Assembly by October 20, 2024 at the latest, before the opening day of the 8th session of the 15th National Assembly.

5. Assign Deputy Prime Minister Tran Hong Ha, Deputy Head of the Standing Committee of the State Steering Committee for important national projects and works, key to the transport sector, to directly direct relevant ministries and agencies to urgently prepare documents and procedures to submit to the National Assembly on schedule and with quality.

6. Regarding investment in the construction of railway lines connecting with China (Lao Cai - Hanoi - Hai Phong, Hanoi - Dong Dang, Mong Cai - Ha Long - Hai Phong): Request the Ministry of Transport to preside over and coordinate with relevant ministries and branches to urgently study investment in the construction of railway lines connecting with China so that investment can be implemented sooner in accordance with the direction of the Prime Minister in Document No. 2771/VPCP-CN dated July 16, 2024, the Government in Resolution No. 37/NQ-CP dated August 15, 2024 and Decision No. 999/QD-TTg dated August 19, 2024; prioritize the implementation of the Lao Cai - Hanoi - Hai Phong railway line first, striving to start construction in 2025.


Comment (0)

No data
No data

Same tag

Same category

Admiring Gia Lai coastal wind power fields hidden in the clouds
Coffee shops in Hanoi are bustling with Mid-Autumn Festival decorations, attracting many young people to experience
Vietnam's 'sea turtle capital' recognized internationally
Opening of the art photography exhibition 'Colors of life of Vietnamese ethnic groups'

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product