Da Nang reclaims nearly 10 hectares of land to serve the Hoa Lien - Tuy Loan expressway

Báo Đầu tưBáo Đầu tư03/08/2024


Da Nang reclaims additional land of nearly 10 hectares to serve the Hoa Lien - Tuy Loan expressway

In 2024, Da Nang will reclaim more than 9.9 hectares of additional land to implement the 220kV High Voltage Power Line Relocation Project and Resettlement Area No. 1 Project to serve the Hoa Lien - Tuy Loan Expressway Project.

The Hoa Lien - Tuy Loan Expressway project is under construction.
The Hoa Lien - Tuy Loan Expressway project is under construction.

At the 19th Session, Term X, the People's Council of Da Nang City approved the Resolution on the List of works and projects requiring additional land acquisition in 2024 of Da Nang City with a total of 23 projects with a total area of ​​over 116 hectares, including the expected additional land acquisition area in 2024 of over 43.6 hectares. Of which, 2 projects requiring additional land acquisition in 2024 serve the Hoa Lien - Tuy Loan expressway project in Hoa Vang district.

Specifically, Da Nang reclaimed 2,429 m2 of land (the entire project area) in Hoa Son commune to serve the Project of Relocating the 220kV high-voltage power line to serve the Project of Building the Hoa Lien - Tuy Loan Expressway section of the North - South Eastern Expressway (expected capital plan in 2024 is 32.04 billion VND).

Next, the City reclaimed an area of ​​97,295 m2 of land in Hoa Nhon commune (total project land area is 109,286 m2) to serve the Resettlement Area Project No. 1 to serve the clearance of the Hoa Lien - Tuy Loan Expressway Construction Project (estimated annual capital plan is 217,748 billion VND). This is a project approved in Resolution No. 32/NQHDND, dated August 12, 2021, which has now been almost 3 years but has not been completed, so it is proposed to continue to be included in the list of projects requiring land recovery.

Regarding the Hoa Lien – Tuy Loan Expressway Project, the People's Committee of Da Nang City said that the project has a total route length of about 11.5 km, passing through 3 communes of Hoa Lien, Hoa Son and Hoa Nhon in Hoa Vang district; the project implementation period is in 2021-2025.

The total investment is 2,112.985 billion VND from the state budget. Of which, the cost of compensation for site clearance including contingency is 951.190 billion VND (the cost of constructing the resettlement area is 105.177 billion VND and relocating the power line is 81 billion VND). The investor of the site clearance sub-project is the Management Board of Infrastructure Development Projects of Da Nang Industrial and High-Tech Parks (hereinafter referred to as the Management Board).

Site clearance progress, as of June 28, 2024, has counted 1,207/1,216 records and counted 2,758 graves; held legal meetings to review 1,043/1,216 records and assessed 952 records.

Da Nang has paid and handed over the site of 832 files, handed over 2,450 graves; the total value of price assessment and approved compensation is 119,389 billion VND, of which 51,906 billion VND has been paid.

By the end of June 2024, the Management Board is completing investment preparation procedures to submit for appraisal and approval of Resettlement Area Project No. 1 to serve the clearance of the Hoa Lien - Tuy Loan Expressway Construction Project (belonging to the North - South Eastern Expressway, Da Nang City); is implementing related procedures to organize the relocation and handover of technical infrastructure of 220kV, 500kV high-voltage lines...

The People's Committee of Da Nang City also informed that for resettlement arrangement, the appraisal and approval of the design of the construction drawings of Resettlement Area Project No. 1 will be completed and construction bidding will be deployed, and construction will be implemented in the third quarter of 2024; the actual land handover for the first resettlement arrangement for the project is expected to be in May 2025, handover in stages according to the resettlement land arrangement progress and completed in 2025.

In 2024, Da Nang will also reclaim more than 18.6 hectares (out of a total area of ​​more than 48.4 hectares) to implement the Project to complete the frontage road along both sides of the southern bypass of Hai Van Tunnel (section from Hoa Lien to Tuy Loan) in the communes of Hoa Lien, Hoa Son, and Hoa Nhon of Hoa Vang district.



Source: https://baodautu.vn/da-nang-thu-hoi-bo-sung-dat-gan-10-ha-de-phuc-vu-cao-toc-hoa-lien---tuy-loan-d221355.html

Comment (0)

No data
No data

Same tag

Same category

Ha Giang - the beauty that holds people's feet
Picturesque 'infinity' beach in Central Vietnam, popular on social networks
Follow the sun
Come to Sapa to immerse yourself in the world of roses

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product