During an on-site inspection of the Dong Viet Bridge access road project connecting to National Highway 37; the road to the Con Son - Kiet Bac historical site (section from National Highway 37 to Con Son Pagoda); and the road to the Con Son - Kiet Bac historical site (half of the left side from An Linh intersection to Dau Rong intersection), Chairman of the Provincial People's Committee Le Ngoc Chau requested relevant units and localities to urgently accelerate progress and complete the road to the Con Son - Kiet Bac historical site (section from National Highway 37 to Con Son Pagoda) for use before the Lunar New Year and spring festivals to serve the transportation needs of the people.

Following the principle of "doing it right the first time," the Chairman of the Provincial People's Committee requested a thorough review and close monitoring of the progress of each item on the construction site, paying attention to investing in a suitable system of trees and lawns that are consistent with the architectural and landscape design.
Expedite the progress of the Dong Viet Bridge access road construction project connecting to National Highway 37, completing the remaining items by January 24th at the latest.

Regarding land clearance, the Chairman of the Provincial People's Committee requested the entire political system to participate, strengthening propaganda and mobilization efforts to help people understand the importance of the projects and create consensus. Appropriate and specific communication content should be developed for each case. During the land clearance process, fairness and the legitimate rights and interests of households must be ensured; the opinions of households should be listened to. For any arising issues, the legal basis should be carefully studied, and they should be resolved definitively.
At the inspection sites, Chairman of the Provincial People's Committee Le Ngoc Chau presented gifts and encouraged officials, engineers, and workers participating in the construction of the projects; he requested the construction units to overcome difficulties, accelerate progress, and ensure the quality of the projects.

The project to build the access road to Dong Viet Bridge connecting to National Highway 37 has completed 95% of its work. Currently, the contractor is implementing the construction of the drainage system, traffic safety measures, sidewalks, etc., and is expected to complete it before January 24, 2025.
Although the approach road to the Dong Viet Bridge on the Hai Duong side is nearing completion, the approach road on the Bac Giang side is still under construction, so it is not yet possible to cross the Dong Viet Bridge.
The project for the road leading to the Con Son - Kiet Bac historical site (the section from National Highway 37 to Con Son Pagoda) is 89% complete. Currently, work is underway to complete the planting and maintenance of trees, cleaning of sidewalks and road surfaces, etc., and is expected to be finished before January 15, 2025, to serve the Con Son - Kiet Bac Spring Festival in 2025.
The project to build the access road to the Con Son - Kiet Bac historical site (half of the left side from An Linh intersection to Dragon Head intersection) has reached approximately 10% completion. Due to numerous obstacles and fragmented land acquisition issues, construction is proving difficult and cannot be carried out simultaneously. It is expected that the contractor will complete the installation of the main road's median strip between now and the Lunar New Year 2025. The section connecting to the Dong Viet access road will continue with drainage, roadbed, and retaining wall construction.
HA NGA - THANH CHUNGSource: https://baohaiduong.vn/day-nhanh-tien-do-thi-cong-duong-vao-khu-di-tich-con-son-kiep-bac-dua-vao-su-dung-truoc-tet-nguyen-dan-402825.html