Hanoi City directed wards to urgently complete site clearance work on the Hoang Cau-Vo Phuc section to serve the Ring Road 1 project.
The Hanoi Party Committee requested the Party Committees and authorities of O Cho Dua, Lang and Giang Vo wards to concentrate resources to complete the site clearance work as soon as possible and strengthen propaganda and mobilization work to create consensus among people whose land is being recovered; and stabilize the situation in the area.
Representative of the Hanoi City Civil Construction Investment Project Management Board said Ring Road 1 project, Hoang Cau - Voi Phuc section There are still many major problems in site clearance. Of these, 222 households have received money and resettlement houses but have not yet handed over the site.
Wards must complete approval of all remaining compensation, support and resettlement plans before November 30 and complete site clearance for the entire route before December 15, 2025.
The People's Committees of wards are having to deploy many measures such as fencing, cutting off electricity and water, and organizing enforcement to reclaim land according to regulations.
To ensure the progress of site clearance, Giang Vo ward will launch a 20-day and night "campaign" determined to complete site clearance for the Ring Road 1 project, Hoang Cau - Voi Phuc section in the area.
Chairman of Giang Vo Ward People's Committee Co Nhu Dung said that as of November 23, the Ring Road 1 construction project, Hoang Cau - Voi Phuc section In the ward, there are a total of 795 site clearance plans, 100% of which have been approved.
There are currently 318 plans that have not yet handed over the land out of a total of 795 plans because some households do not agree with the state's compensation policy and some other objective reasons.

The City Party Committee has assigned Giang Vo Ward to carry out a 20-day campaign to complete site clearance before December 15, 2025. The Ward is continuing to mobilize households to receive compensation and hand over the site.
For households that do not hand over even though they have received money or resettlement houses, the ward will report to the City People's Committee to consider reclaiming resettlement apartments and rearranging them according to regulations; at the same time, apply measures to stop supplying electricity, water, and fences to serve the forced reclamation of the site.
At the same time, continue to clarify the problems and reasons why households have not yet handed over the premises; continue to propagate and mobilize households to receive money, receive houses and hand over the premises according to regulations.
Source: https://baolangson.vn/ha-noi-yeu-cau-cac-phuong-hoan-thanh-som-nhat-giai-phong-mat-bang-doan-hoang-cau-voi-phuc-5065991.html






Comment (0)