- On May 8, Comrade Luong Trong Quynh, Vice Chairman of the Provincial People's Committee, Head of the Steering Committee for implementing key projects chaired a meeting to review the implementation of key projects in the first quarter and deploy key tasks in the second quarter.
In 2025, the Provincial People's Committee selected 22 projects to focus on leading and directing to accelerate progress, including 6 projects using state budget capital, 5 projects invested under the public-private partnership method and 11 projects using non-budget capital; the total investment of the projects is more than 51.8 trillion VND.
Regarding implementation progress, as of early May 2025, there were 4 projects using public investment capital meeting progress requirements, 2 projects behind schedule; 2 public-private partnership projects meeting progress requirements, 4 projects behind schedule; 4 off-budget projects meeting progress requirements, 7 projects behind schedule.
Regarding capital disbursement for public investment projects, there are 4 projects with cumulative disbursement up to the end of the first quarter of 2025 of 1,573/4,375 billion VND, equivalent to 35.9% of the total investment; 2 projects have not yet had disbursement results. Regarding the disbursement of 5 investment projects in the form of public-private partnership, there are 2 projects with cumulative disbursement up to the end of the first quarter of 2025 of 2,269 trillion VND, 3 projects have no disbursement data. For 11 non-budget investment projects, 5 projects have disbursement results with a total amount of 930 billion VND, 6 projects have no disbursement data.
Discussing at the meeting, representatives of investors requested the Provincial People's Committee to direct the People's Committees of districts to continue to pay attention to removing difficulties and obstacles to speed up the progress of site clearance for projects; move technical infrastructure works ; direct departments and branches to advise on appraisal of documents, carry out land lease, land allocation for project implementation and support investors in completing legal procedures.
The People's Committees of districts and departments and branches recommend that investors continue to coordinate and arrange sufficient capital to pay for approved compensation plans, strictly implement the reporting regime as well as develop a project implementation plan in 2025.
Concluding the meeting, the Vice Chairman of the Provincial People's Committee acknowledged the efforts of investors and the People's Committees of districts in carrying out site clearance for key projects with many positive changes, and difficulties and obstacles were promptly resolved.
Regarding the tasks in the coming time, he requested: Investors strictly implement the direction of the Provincial People's Committee on developing a project implementation plan in 2025 and send it to the Provincial People's Committee and relevant departments and branches for monitoring, urging and management.
For the People's Committees of districts and cities, continue to focus on directing the acceleration of progress, and coordinate with departments and branches to promptly resolve problems arising in the site clearance of projects. In particular, the People's Committees of districts must focus on resolving the site clearance of expressway projects in accordance with the direction of the provincial leaders in May 2025 and speed up the construction of resettlement areas.
Investors of public investment projects closely follow the site, urge contractors to speed up the construction progress of projects and urgently complete the procedures for new projects to start construction in July 2025. The functional departments and branches assigned to monitor and urge key projects continue to closely follow each project to urge and support investors and project owners, speed up the implementation progress and report the implementation status monthly.
Source: https://baolangson.vn/hop-kiem-diem-du-an-trong-diem-quy-i-2025-5046360.html