According to the report, Lam Dong Provincial Agricultural Project Management Board was assigned a total capital of VND 877,432 billion to implement 41 projects in 2025.
The capital sources are diversified, including: 490,538 billion VND from the central budget for 6 projects; 5.7 billion VND of ODA capital for 1 transitional project; 82,236 billion VND of domestic capital for 23 projects; 13,758 billion VND from land use fee revenue for 6 projects; 200 million VND from lottery revenue for 2 projects preparing for investment; and 285 billion VND from capital managed by the Ministry of Agriculture and Environment for 3 projects.
As of October 22, Lam Dong Provincial Agricultural Project Management Board has disbursed VND 416,151 billion, reaching 47.43% of the 2025 plan; it is expected to reach VND 495,658 billion by October 30, equivalent to 56.53%.
Of which, some projects have positive disbursement progress, typically the Ka Pet Reservoir Project with a total investment of VND 874,089 billion, the capital plan for 2025 is VND 267,517 billion, of which VND 188,745 billion has been disbursed, reaching 70.55%.
The project to complete the Song Mong reservoir canal system has a total investment of VND89,989 billion, and is expected to complete the disbursement of the entire 2025 capital plan of VND1,471 billion before October 30.
The project to complete the irrigation system of Ta Pao, with a total investment of 99,201 billion VND, is expected to disburse 100% of the capital in 2025, which is 33,843 billion VND, before November 13.
However, the Agricultural Project Management Board said that the implementation process still faces many difficulties, especially in compensation, support and resettlement when reclaiming land, causing some projects to be at risk of not being completed in 2025. The unit proposed to extend the implementation progress until the end of 2026 to ensure effective implementation and meeting the set goals.
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Ngoc Phuc requested investors to urgently review and evaluate the progress of each project and proactively propose solutions to remove obstacles, especially in site clearance, to speed up construction progress and ensure the disbursement plan for public investment capital.
The ultimate goal is to soon put the projects into operation, promote investment efficiency, contribute to promoting local socio-economic development, especially irrigation works that play an important role in irrigation and minimizing damage caused by floods.