Bien Hoa completed handing over 100% of the land to implement the Bien Hoa - Vung Tau Expressway Project.

On April 18, Member of the Provincial Party Standing Committee, Secretary of Bien Hoa City Party Committee Ho Van Nam inspected the site clearance work for the Bien Hoa - Vung Tau Expressway Project through Bien Hoa City and the Huong Lo 2 Project (section 1, phase 1) through Long Hung Commune, Bien Hoa City.

Báo Đồng NaiBáo Đồng Nai18/04/2025

The Bien Hoa - Vung Tau Expressway Project's section through Bien Hoa city has been 100% handed over.
The Bien Hoa - Vung Tau Expressway Project's section through Bien Hoa City has been 100% handed over. Photo: Khac Thiet

Through the inspection of the Bien Hoa - Vung Tau Expressway Project through Bien Hoa City, it was found that the entire project site through Bien Hoa City has been cleared, and the construction contractors are focusing on many construction teams to implement the roadbed construction. There are still a few works that are brick walls that have not been leveled, Bien Hoa City Party Secretary Ho Van Nam requested the Ward People's Committee to coordinate with the contractor to level the ground on the same day to hand over clean land for the project construction.

Chairman of Phuoc Tan Ward People's Committee Le Kim Huong said that the last two households subject to clearance for the project's construction section through the ward have also agreed to commit to handing over the site and self-demolishing the project. Thus, up to now, a total of 1,514/1,514 households, representatives of organizations and enterprises subject to clearance for the Bien Hoa - Vung Tau Expressway Project through Phuoc Tan and Tam Phuoc wards, Bien Hoa city have handed over the site with a total area to be recovered of 59.5 hectares, reaching 100%.

Member of the Provincial Party Standing Committee, Secretary of Bien Hoa City Party Committee Ho Van Nam inspected the site clearance of the Bien Hoa - Vung Tau Expressway Project, section through Phuong Tan ward on the morning of April 18.
Member of the Provincial Party Standing Committee, Secretary of Bien Hoa City Party Committee Ho Van Nam inspected the site clearance of the Bien Hoa - Vung Tau Expressway Project through Phuong Tan Ward on the morning of April 18. Photo: Khac Thiet

On the same day, inspecting the site clearance work at Huong Lo 2 Project through Long Hung Commune, Bien Hoa City Party Secretary Ho Van Nam directly visited a number of households to grasp the thoughts and aspirations of the households whose land was cleared and recovered for the project. For the recommendations that had a basis for resolution for the people, Bien Hoa City Party Secretary directly directed the Bien Hoa City Land Fund Development Center to immediately handle them for the households, other problems that needed to be reviewed must also be handled and answered to the people within the day.

Through inspection and understanding from the people, the Secretary of Bien Hoa City Party Committee assessed that the agencies and localities that have carried out compensation support work when the State reclaims land in the past have been too rigid, even showing signs of "playing around", causing people to lack trust and therefore have not yet handed over the land.

A construction site at the beginning of Dinh Quang An Street is focusing on roadbed construction
A construction team at the beginning of Dinh Quang An Street is focusing on constructing the roadbed. Photo: Khac Thiet

“The project's site clearance has lasted for more than 5 years, but until now, people still do not know which agency to go to to receive compensation support money when the State reclaims land, do not know who to contact to receive money, and how to receive resettlement land, showing that the officials in charge of compensation and support in the past have not fulfilled their responsibilities and have not been close to the people" - Bien Hoa City Party Secretary Ho Van Nam emphasized.

Bien Hoa City Party Secretary Ho Van Nam and the city's working delegation listened to the thoughts and aspirations of people subject to clearance for the Huong Lo 2 project through Long Hung commune. Photo: Khac Thiet

After the first 2 days of the mobilization delegation of the Bien Hoa City Party Committee Standing Committee directly visiting households to propagate and mobilize, more than 10 households have handed over land for project construction. The City Party Committee Secretary requested the local government and the City Land Fund Development Center to coordinate with the construction unit to focus on dismantling and leveling the land that households have handed over for project construction, especially the area of ​​the An Hoa 2 bridge abutment and pier on the bank of Long Hung commune.

Currently, the area of ​​the bridge piers and abutments is basically clear. The construction unit representative said that they will transport machinery and human resources to drill bored piles to construct the bridge in the next few days.

Carving

Source: https://baodongnai.com.vn/kinh-te/202504/bien-hoa-hoan-thanh-ban-giao-100-mat-bang-thuc-hien-du-an-duong-cao-toc-bien-hoa-vung-tau-d702f23/


Comment (0)

No data
No data

Same category

Find your own Northwest
Admire the "gateway to heaven" Pu Luong - Thanh Hoa
Flag-raising ceremony for the State funeral of former President Tran Duc Luong in the rain
Ha Giang - the beauty that holds people's feet

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product