Currently, contractors are speeding up the construction progress of Dong Viet Bridge, striving to open it to technical traffic in early September, nearly 4 months ahead of schedule (December 24, 2024).
Mr. Nguyen Dinh Thang - Deputy Commander of the Dong Viet Bridge Project Joint Venture said that at this time, the bridge and the approach road are being constructed on schedule. Contractors are focusing on constructing the railing system, completing the embankment, median strip, concrete pavement, and installing the lighting system.
On the Hai Duong province side, the construction unit of Dong Viet bridge approach road connecting to National Highway 37 is paving asphalt concrete, at the same time carrying out drainage, tree planting, slope reinforcement, and construction of traffic safety system including installation of signs, line painting, guardrail installation, and marker posts...
The Dong Viet Bridge project was started in June 2022 with a total investment of nearly 1,500 billion VND. The project is invested by the Management Board of Investment and Construction Projects for Transport and Agricultural Works of Bac Giang Province. This is the largest cable-stayed bridge in Bac Giang Province, crossing the Thuong River to connect with Hai Duong Province.
When completed, Dong Viet Bridge will help people travel conveniently and safely. The project is expected to promote the circulation of goods between Bac Giang and Hai Duong provinces, develop tourism, and create favorable conditions to attract investors to industrial parks and clusters in Bac Giang province.
Dong Viet Bridge is more than 730m long, the bridge surface is 22.5m wide. The main bridge consists of 2 cable-stayed spans, one flat surface, the approach bridge consists of 14 Super T spans.
Dong Viet Bridge is built on a permanent bridge scale using reinforced concrete and prestressed reinforced concrete structures.
The cable bundles are installed parallel to the construction of the cantilever box girder section with a distance of 9m/bundle. 24 cable bundles in 2 cable-stayed spans are the main load-bearing structure of Dong Viet Bridge.
Inside each cable-stayed structure are many cables bundled together to ensure the bridge can withstand the safe load according to the design.
The road leading to the bridge on both sides is about 7.86km long, with a level II plain road scale, 22m base, 21.5m road surface.