The starting point of Phong Dien railway overpass is paved with asphalt concrete.

Phong Dien-Dien Loc road project, with a total investment of more than 754 billion VND, 16.25km long, 36-42.5m wide road surface, sidewalks, trees, drainage system on both sides... in which the railway overpass project in Phong Thu ward (Phong Dien town) is allocated a construction investment of more than 65.44 billion VND.

The overpass is designed to include 2 units, 31m wide, more than 66.3m long with a pile system, T1 and T2 pier bases, retaining walls..., starting construction in 2022. Up to this point, the overpass project has reached nearly 99% of the plan (currently carrying out the final stage of paving the bridge surface with asphalt concrete and installing the railing system on the left unit to be completed before June 15).

The left side of the overpass is paved with asphalt concrete, preparing for synchronous traffic.

Mr. Nguyen Van Cuong, Deputy Director of the Hue City Traffic Construction Project Management Board, said that the overpass is the main item in the Phong Dien - Dien Loc road project. This project will build 5 bridges, including 1 large bridge, 4 medium bridges, including the Phong Dien railway overpass. When the railway overpass is completed and put into use, it will help the Phong Dien - Dien Loc road project reach the finish line soon to connect with National Highway 1A, National Highway 49B, Provincial Road 4 and many other residential roads; at the same time, reduce traffic conflicts between railways and roads in the southern gateway area of ​​Phong Thu ward (Phong Dien town).

According to the Management Board of the Hue City Traffic Construction Investment Project, up to now, the Phong Dien-Dien Loc Road Project has been allocated capital of more than 666 billion VND; of which more than 621 billion VND has been disbursed.

Song Minh