Vietnam.vn - Nền tảng quảng bá Việt Nam

The large construction site creates the shape of a seaport at the foot of Hai Van Pass

(Dan Tri) - With the construction reaching more than 85% of the contract value of the shared infrastructure for the Lien Chieu port project. The shape of a "super seaport" at the foot of Hai Van Pass (Da Nang) is gradually taking shape.

Báo Dân tríBáo Dân trí07/06/2025

1.webp

Lien Chieu Port started construction on December 14, 2022 with a total planning area of ​​1,285 hectares. The port is located at the foot of Hai Van Pass, in Hoa Hiep Bac Ward (Lien Chieu District, Da Nang ). The south is planned to border the Cu De River mouth, the east is planned to border Da Nang Bay.

2.webp

The shared infrastructure of Lien Chieu port has a total investment of 3,462 billion VND from the state budget, expected to be completed in November. In the photo is a perspective of Lien Chieu seaport (Graphics: Phu Xuan Consulting and Construction Joint Stock Company ).

3.webp

According to the Management Board of Priority Infrastructure Investment Projects in Da Nang, the shared infrastructure part of the Lien Chieu port project has completed 85.6% of the contract value.

4.webp

According to the announced plans, Lien Chieu port includes 8 container berths to receive ships of 30,000-200,000 DWT, 6 general berths to receive ships of 30,000-100,000 DWT, a berth for SB ships of 1,230m long...

The port is planned to reduce the load on the existing Tien Sa port, reduce pressure on road traffic passing through Da Nang city center, strengthen regional and inter-regional connectivity, and contribute to the sustainable socio -economic development of Da Nang and the region.

5.webp

Thousands of cubic meters of earth and rock were dumped into the sea to form a system of dikes and breakwaters from afar.

6.webp

Workers have been rushing to speed up progress, making efforts to complete the breakwater project at the foot of Hai Van Pass soon.

7.webp

A breakwater section has been completed in the coastal area of ​​Hoa Hiep Bac ward.

8.webp

Despite the hot weather, workers still tried to complete the construction items to meet the city's schedule.

9.webp

Along with Lien Chieu port, the coastal road project connecting Lien Chieu port, with a total investment of 1,203 billion VND, nearly 3km long with many bridges, overpasses, underpasses, modern traffic intersections... is also under construction.

10.webp

The project started on September 8, 2023 and is expected to be completed in February 2026.

According to the Management Board of Priority Infrastructure Investment Projects in Da Nang, the project has completed 62% of the contract value.

11.webp

Location of Lien Chieu seaport, Da Nang city (Photo: Google Maps ).

Dantri.com.vn

    • Source: https://dantri.com.vn/xa-hoi/dai-cong-truong-dung-nen-hinh-hai-cang-bien-duoi-chan-deo-hai-van-20250606212937869.htm

Comment (0)

No data
No data

Same tag

Same category

Thanh Hoa coastal wooden bridge causes a stir thanks to its beautiful sunset view like in Phu Quoc
The beauty of female soldiers with square stars and southern guerrillas in the summer sun of the capital
Forest festival season in Cuc Phuong
Explore Hai Phong culinary tour

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product