The large construction site creates the shape of a seaport at the foot of Hai Van Pass

(Dan Tri) - With the construction reaching more than 85% of the contract value of the shared infrastructure for the Lien Chieu port project. The shape of a "super seaport" at the foot of Hai Van Pass (Da Nang) is gradually taking shape.

Báo Dân tríBáo Dân trí07/06/2025

1.webp

The Lien Chieu Port project commenced on December 14, 2022, with a total planned area of ​​1,285 hectares. The port is located at the foot of the Hai Van Pass, in Hoa Hiep Bac ward (Lien Chieu district, Da Nang ). Its southern boundary is adjacent to the Cu De River estuary, and its eastern boundary is adjacent to Da Nang Bay.

2.webp

The shared infrastructure of Lien Chieu Port has a total investment of 3,462 billion VND from the state budget, and is expected to be completed in November. The image shows a rendering of Lien Chieu seaport (Graphic: Phu Xuan Consulting and Construction Joint Stock Company ).

3.webp

According to the Da Nang Priority Infrastructure Investment Projects Management Board, the shared infrastructure portion of the Lien Chieu port project has reached 85.6% of the contract value.

4.webp

According to the published plans, Lien Chieu port will include 8 container berths capable of receiving vessels of 30,000-200,000 DWT, 6 general cargo berths capable of receiving vessels of 30,000-100,000 DWT, and a berth for SB vessels up to 1,230m long…

The port is planned to alleviate congestion at the existing Tien Sa port, reduce pressure on road traffic through Da Nang's inner city, enhance regional and inter-regional connectivity, and contribute to the sustainable socio -economic development of Da Nang and the region.

5.webp

Thousands of cubic meters of earth and rock were dumped into the sea to shape the system of dikes and breakwaters extending from the seaward side.

6.webp

Workers have been working diligently to speed up progress and complete the breakwater project at the foot of Hai Van Pass as soon as possible.

7.webp

A section of breakwater has been completed in the coastal area of ​​Hoa Hiep Bac ward.

8.webp

Despite the hot weather, the workers are still striving to complete the construction projects in order to meet the city's deadlines.

9.webp

Along with Lien Chieu Port, the coastal road project connecting Lien Chieu Port, with a total investment of 1,203 billion VND, is nearly 3km long and includes many bridges, overpasses, underpasses, and modern traffic junctions… and is also under construction.

10.webp

The project commenced on September 8, 2023, and is expected to be completed in February 2026.

According to the Da Nang Priority Infrastructure Investment Projects Management Board, the project has completed 62% of the contract value.

11.webp

Location of Lien Chieu seaport, Da Nang city (Photo: Google Maps ).

Dantri.com.vn

    • Source: https://dantri.com.vn/xa-hoi/dai-cong-truong-dung-nen-hinh-hai-cang-bien-duoi-chan-deo-hai-van-20250606212937869.htm

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Don Den – Thai Nguyen's new 'sky balcony' attracts young cloud hunters

News

Political System

Destination

Product