Deadline for handover of Ho Chi Minh road site, eastern bypass of Buon Ma Thuot city

The Ministry of Construction has just issued an official dispatch on coordinating direction and finalizing the site clearance work for the Ho Chi Minh Road Construction Investment Project, Eastern bypass of Buon Ma Thuot City (project).

Báo Đắk LắkBáo Đắk Lắk22/05/2025

During the project implementation process, the Ministry of Construction sent many documents to the Dak Lak Provincial People's Committee requesting support to speed up the site clearance progress and complete the handover of the entire site for the project before May 15, 2025.

In the past time, the locality has resolved some existing problems and difficulties such as: Completed the relocation of the T20 power pole at Km32+600, and handed over the entire site through Buon Ma Thuot City. However, there are still 113m of the section through Cu M'gar district and local problems at some locations of the drainage ditches through Krong Pac and Cu Kuin districts that have not been completely resolved.

To ensure the completion of the project before June 30, 2025, the Ministry of Construction requested the Provincial Party Secretary and Chairman of the Dak Lak Provincial People's Committee to continue to direct relevant units of the province to speed up site clearance work, and complete the handover of the entire site for the project before May 30, 2025.

The project is currently stuck with a clearance of more than 100m in the section passing through Cuor Dang commune, Cu Mgar district.
The project is currently stuck with a clearance of more than 100m in the section passing through Cuor Dang commune, Cu M'gar district.

In particular, focus on implementing a number of contents: Directing the People's Committee of Cu M'gar district to promptly organize the approval of compensation and support plans when the state reclaims land to have a basis for making payments to people, handing over the construction site for 113m of the main route and the scope of 2 spillways (the spillway on National Highway 14 and the spillway at Km1+700); directing the People's Committee of Krong Pac district to strengthen propaganda, mobilization, and take measures to organize construction protection for the remaining 2 households to have a construction site to complete the access canal No. 2 at Km13+203; directing the People's Committee of Cu Kuin district to promptly organize the payment to people, hand over the construction site for the scope of access canal No. 5 at Km15+511.

In case the site clearance work of the Project continues to be delayed and does not meet the requirements for the implementation and completion of the Project, the Ministry of Construction requests the leaders of Dak Lak province to consider handling the responsibilities of relevant collectives and individuals.

As of May 30, 2025, if there are still problems with the site, the Ministry of Construction will consider zoning the Project to hand over to the locality for management and investment completion after the locality has arranged funding sources.

Source: https://baodaklak.vn/kinh-te/202505/chot-thoi-han-ban-giao-mat-bang-duong-ho-chi-minh-doan-tranh-phia-dong-tp-buon-ma-thuot-bd52069/