Chairman of An Giang Provincial People's Committee Ho Van Mung inspected the construction progress of Chau Doc - Can Tho - Soc Trang expressway, the section passing through the province.

On April 5, Alternate member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, Chairman of the An Giang Provincial People's Committee Ho Van Mung led a provincial delegation to inspect the construction progress of Component Project 1 of the Chau Doc - Can Tho - Soc Trang Expressway Project Phase 1, the section passing through An Giang province.

Báo An GiangBáo An Giang05/04/2025

Chairman of An Giang Provincial People's Committee Ho Van Mung directly inspected the project construction sites in Thoai Son, Chau Thanh, Chau Phu districts, Chau Doc city and listened to construction units report on the project construction progress.

Up to now, the total output of the 4 main construction packages is 47.8%/ 47.56% (exceeding about 0.24%) compared to the contract value.

Chairman of An Giang Provincial People's Committee Ho Van Mung shared the difficulties in the construction process and encouraged engineers and workers at the construction site.

Directly inspecting the project construction sites in Thoai Son, Chau Thanh, Chau Phu districts, Chau Doc city and listening to the construction units report on the project construction progress. Accordingly, up to now, the total output of the 4 main construction packages is 47.8%/47.56% (exceeding about 0.24%) compared to the contract value, Chairman of An Giang Provincial People's Committee Ho Van Mung commended and acknowledged the efforts of relevant departments, investors, construction units and local authorities in organizing the implementation of the project ahead of schedule. At the same time, he shared the difficulties in the construction process and encouraged the engineers and workers at the construction site.

The Chairman of the Provincial People's Committee emphasized that the difficulties and problems related to stone and sand materials have been resolved by the leaders of An Giang province, therefore, contractors must adjust the plan to complete the project before June 30, 2026 according to the direction of the Prime Minister. Comrade Ho Van Mung suggested that the Provincial Project Management Board work with consultants to implement the recommendations of some contractors on construction solutions. In particular, the adjustment of construction solutions must still ensure the important factor of construction quality, not allowing the adjustment of construction solutions to be made without approval from competent authorities. Antraco Joint Venture Company Limited proactively coordinates with units in arranging the gathering of stone materials to ensure both the company's operations and the supply of materials to contractors on schedule. Request Antraco Joint Venture Company Limited to control the supply of stone materials in accordance with the adjustment license.

Chairman of An Giang Provincial People's Committee Ho Van Mung requested contractors to proactively work with sand suppliers according to the confirmation tables; not to affect environmental issues, river transport, not to exploit beyond depth, beyond capacity... Request Truong Son Construction Corporation to submit documents to the Provincial People's Committee to adjust the confirmation table to mobilize sand volume to serve the remaining needs of the bid packages. Assign the Department of Agriculture and Environment, the Provincial Project Management Board to preside over and coordinate with Truong Son Construction Corporation and contractors to supply sand in accordance with regulations and ensure progress for the bid packages. The Department of Agriculture and Environment continues to monitor the sand exploitation of sand mines, in accordance with legal regulations, and not to allow violations to occur.

Chairman of An Giang Provincial People's Committee Ho Van Mung especially reminded the contractors to commit to strictly following the Prime Minister's direction, completing the project before June 30, 2026. At the same time, he requested that the contractors continue to uphold their sense of responsibility, make more efforts, be more determined, work in the spirit of "overcoming the sun, overcoming the rain", "eating quickly, sleeping urgently", working "3 shifts, 4 shifts", "through holidays, through Tet" to speed up the construction progress of the project, strive to complete ahead of schedule for each project item and the whole project, bringing the project to the finish line on schedule.

TRUST

Source: https://baoangiang.com.vn/chu-tich-ubnd-tinh-an-giang-ho-van-mung-kiem-tra-tien-do-thi-cong-cao-toc-chau-doc-can-tho-soc-t-a418324.html


Comment (0)

No data
No data

Same category

What do you need to prepare when traveling to Sapa in the summer?
The wild beauty and mysterious story of Vi Rong cape in Binh Dinh
When community tourism becomes a new rhythm of life on Tam Giang lagoon
Ninh Binh tourist attractions not to be missed

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product