Accordingly, the Department of Construction directed the Da Nang Drainage and Wastewater Treatment Company to urgently preside over and coordinate with relevant units to mobilize all available forces to organize a site inspection, clear and clean up all inlets and water intake ditches under its management; promptly remove odor-blocking covers arbitrarily installed by residents; and temporary dams at drainage outlet locations.
At the same time, arrange human resources to deploy on-duty work, prepare means and equipment to promptly handle at key drainage locations, at risk of flooding in urban areas such as: Hai Ho street area; Nui Thanh street; Nguyen Van Linh, Ham Nghi, Le Duan, Hoang Hoa Tham, Ong Ich Khiem streets; downstream of Khe Can; Ha Huy Tap street, Nguyen Trac street (K5 lake area),...
The company coordinated to lower the water level at the regulating lakes to the lowest possible level (29-3 Park Lake, Thac Gian - Vinh Trung Lake, K5 Lake, etc.) to maximize the ability to regulate water when heavy rain occurs; coordinated with relevant units to effectively implement urban flooding response scenarios and scenarios to respond to and overcome incidents of wastewater overflowing into the sea, ensuring maximum limitation of localized flooding and coastal environmental pollution.
For anti-flood pumping stations (Thuan Phuoc, Truong Chi Cuong, K20, Dao Xanh, Ong Ich Khiem, Yen Khe 2), the company urgently checks the power source and related issues to ensure the pumping station operates stably; checks the operation of the trash screen at the pumping station, arranges personnel to be on duty regularly, monitors and promptly handles incidents at the pumping station.
The company is ready with high-capacity pumps to promptly handle flooding in low-lying residential areas and localized flooding due to slow drainage.
The Department of Construction requested the People's Committees of districts to direct the People's Committees of wards and communes and local drainage units to review and deploy the clearing of all water intakes on roads under their management; at the same time, step up propaganda and mobilize people to join hands in flood prevention; clear water intakes, remove odor-blocking covers on intakes to maximize the exploitation of the current drainage system.
In addition, organize forces to guard and block deep flooded areas, especially areas with strong and dangerous water flows, to promptly handle complicated situations and provide rescue support if they occur; effectively deploy urban flood response scenarios in areas at risk of flooding within the management area.
Investors and project management units direct contractors to arrange personnel to regularly be on duty at unfinished construction sites and immediately implement temporary drainage solutions, especially at locations that have not been fully connected to drainage, have been flooded or are at risk of flooding.
HOANG HIEP