This year, the weather was unfavorable, from May to September heavy rains lasted for a long time, causing some public roads under construction of the Tuyen Quang - Ha Giang expressway to be washed away by floods and landslides, making it impossible to dig, build roadbeds, and transport concrete to serve the construction of bridges, culverts, and underpasses for people.
In many areas, the water level rose so high that it submerged the bridge piers, making construction impossible. The entire route was halted during the rainy months, which greatly affected progress.

Ha Giang approved a resolution to adjust the Tuyen Quang - Ha Giang expressway project (phase 1)
Since the beginning of October, the weather has been dry, which is the “golden period” for construction, especially for projects that are heavily affected by weather factors. Therefore, businesses have mobilized machinery and human resources, dividing into many construction teams along the entire route.
![]() |
In package 03-XL, construction units mobilized many machines and equipment to roll the Tuyen Quang-Ha Giang highway. |
On the construction site of the section from Km19-Km27+480 (package 05-Xl), the sounds of excavators, trucks, and road rollers echoed throughout the site. This section is being constructed by 307 Ha Giang Company Limited and is currently mobilizing hundreds of machines, equipment, and manpower to level mountains, cut hills, and open roadbeds; construct mechanical ditches, top ditches, and cover the road.
Mr. Tran Trung Tinh, construction site manager, 307 Ha Giang Company Limited said: “The highway section constructed by the company has a very complex terrain, with many high mountains and deep ravines, so the roadbed excavation part has a very large volume of excavation and filling, up to nearly 2 million m3. This is a part of the work that is greatly affected by weather factors. Therefore, taking advantage of favorable weather, the company is mobilizing human resources, machinery, and construction in “3 shifts, 4 teams”, so far this part of the work has completed more than 65% of the workload”.
![]() |
307 Ha Giang Company mobilized maximum manpower and machinery to construct the roadbed. |
Similarly, in package 04-XL, the construction of the roadbed for the entire route is being focused on by businesses. To maximize the use of human resources and machinery, businesses are divided into many construction teams along the entire route. In some sections, excavators and cars are mobilized to clear mountains and cut hills to open the roadbed; in other sections, K95 embankment is being constructed, and drainage systems, civil underpasses, bridges and intersections are being constructed along the entire route.
![]() |
Nearly 100 pieces of machinery and human resources are divided into many construction teams on the entire highway in package 04-XL. |
Mr. Nguyen Xuan Tung, Executive Director of Package 04-XL, said: "The entire construction site is racing against time to make up for the work delayed due to floods and storms, ensuring the project is completed by the end of 2025 in accordance with the Prime Minister 's direction."
According to the report of the Management Board of Investment and Construction of Traffic Works of Ha Giang province, the construction progress of the Tuyen Quang-Ha Giang Expressway project (phase 1) through Ha Giang province meets the scope of the handed over land; the project's output as of early November reached nearly 40% of the contract value.
![]() |
Project management staff are regularly present at the site to inspect and urge the construction unit to speed up progress. |
Currently, it is the peak construction period, so businesses are deploying many construction teams, mobilizing thousands of staff, workers and nearly 400 pieces of machinery. Many sections are continuously implementing construction in 3 shifts per day, especially for the items of digging and filling the roadbed, building bridges along the entire route.
Mr. Le Manh Dung, Acting Director of the Ha Giang Province Traffic Construction Investment Management Board, said that in response to the Prime Minister's "500 days and nights of competition to complete 3,000km of expressways"; the 60-day and night competition to disburse public investment capital launched by Ha Giang Province. The leaders of Ha Giang Province, Bac Quang District, and the leaders of the project management board are regularly present at the expressway construction site to inspect, urge, and encourage the construction units to speed up the project implementation progress. Along with that, they are solving difficulties and problems in the implementation process.
![]() |
Construction units strive to complete the roadbed opening before next year's rainy season. |
To ensure the project's construction progress, the Ha Giang Province Traffic Construction Investment Management Board also needs the province, district and relevant agencies to promptly resolve some difficulties.
Resolutely resolve existing problems related to compensation, site clearance, relocation of technical infrastructure and site handover. Currently, there are still some sections and construction bottlenecks along the entire route due to site clearance problems that need to be resolved, including: 636m of site handover has not been completed, some households have not agreed to the compensation price; moving technical infrastructure out of the construction area.
Currently, construction contractors have made many efforts to find sources of stone materials to mobilize and gather at the site. Currently, the stone mines are almost at the approved exploitation capacity in 2024, not ensuring the reserve supply for the project. Therefore, the Department of Natural Resources and Environment will soon remove difficulties in material sources to implement the project.
![]() |
The construction unit urgently carried out boring of the bridge foundation at Km19+350. |
Consider providing additional capital for the 2024 plan to implement the project. According to the supervision consultant's report on quality management records, the completion records of items implemented on site that have been confirmed and accepted by the supervision consultant are eligible for payment to the construction contractor as of October 1, which is 513 billion VND (of which 258 billion has been paid and recovered in advance, and the unpaid value is 255 billion VND).
Source: https://nhandan.vn/ha-giang-day-nhanh-tien-do-thi-cong-cao-toc-tuyen-quang-ha-giang-giai-doan-1-post843859.html
Comment (0)