Senior Lieutenant General Hoang Xuan Chien - Deputy Minister of National Defense - this morning inspected and worked with the Ho Chi Minh Mausoleum Command on the progress of the project "Investment in building infrastructure to serve the reception and propaganda work of the Ho Chi Minh Mausoleum Management Board".

According to the decision approved by the Minister of National Defense, the project's goal is to complete the grass plots south of the square to ensure the architectural landscape of the Ho Chi Minh Mausoleum and Ba Dinh Square; enhance the architectural aesthetics and solemnity of the Mausoleum; contribute to serving the people and international visitors thoughtfully and safely.

w expand ba dinh square 21 of 31 2917.jpg
The areas adjacent to Chua Mot Cot and Ba Huyen Thanh Quan streets (Ba Dinh ward, Hanoi ) were dismantled and installed with auxiliary systems. Photo: The Bang

The project was implemented from June 9, including the following items: demolishing 4 villas in the area south of Ba Dinh Square; expanding 4 rows of grass plots to the south of the square's lawn; building security fences on Doc Lap and Chua Mot Cot streets; building and supplementing information, radio and television systems in the area south of the square.

In addition, the project will build and supplement an automatic sprinkler system, manual irrigation and drainage system for the expanded grass plot area, the area adjacent to the existing grass plots; install lighting systems for roads, lawns, sidewalks, and chandeliers; pour concrete and treat the surface of the expanded Hung Vuong road, make raised gravel sidewalks and walking paths.

Up to now, after 52 days of implementation, the items have been completed ahead of schedule, targets and requirements.

In the coming time, the unit will focus on completing the project documents; continue to monitor, maintain the project, and take care of the lawn to ensure the tasks of the parade, the parade to celebrate the 80th anniversary of the August Revolution and National Day September 2; carry out payment and final settlement of the project completion.

Concluding the inspection, Senior Lieutenant General Hoang Xuan Chien acknowledged, commended and highly appreciated the agencies and units for their promptness, determination and determination in basically completing the project with 7 items. He also requested the agencies and units to continue to supplement and complete the details of the items; continue to care for and maintain the grass, and improve the surrounding landscape.

Senior Lieutenant General Hoang Xuan Chien also requested the Ho Chi Minh Mausoleum Command to establish a regular system, strengthen absolute security for the project; organize acceptance, completion, settlement, and report to the Ministry of National Defense according to regulations; carry out well the emulation and reward work, and motivate officers, employees, and workers directly performing their tasks.

Source: https://vietnamnet.vn/hoan-thanh-vuot-tien-do-du-an-mo-rong-quang-truong-ba-dinh-2427800.html