The railway industry stopped running 45 trains and transferred 3,400 passengers by car.

Due to the impact of storm No. 13 causing a landslide on the railway at Km 1136+800 to Km 1136+925 in the Van Canh - Phuoc Lanh section on the North - South railway line through the two provinces of Dak Lak and Gia Lai, by the morning of November 9, the railway industry had stopped running 45 passenger trains from Hanoi to Ho Chi Minh City and Da Nang to Ho Chi Minh City.

Báo Tin TứcBáo Tin Tức09/11/2025

Photo caption
The Railway Industry organizes passenger transport on trains passing through the area. Photo: Van Son/Tin Tuc Va Dan Toc Newspaper

At this time, the railway industry also reduced the frequency of passenger trains running through the area under construction at Van Canh - Phuoc Lanh section.

At the same time, the railway industry has organized road transport from Dieu Tri station to Tuy Hoa for other trains that are still running. Statistics up to this point show that the number of passengers that have been transferred is more than 3,500 people from 21 passenger trains affected by storm No. 13.

Previously, at km 1136+850, the North-South railway section passing through Dak Lak and Gia Lai provinces in the Phuoc Lanh - Van Canh section encountered a serious incident when the rock foundation was washed away with an average depth of about 9m. In addition, fallen trees blocked the way, broke signal poles, and the national grid lost power, leading to loss of communication and dispatching, and many signal communication devices were paralyzed due to flooding...

As of the morning of November 9, three Railway Joint Stock Companies: Phu Khanh, Nghia Binh and Thuan Hai are installing stone cages on both sides of the bridge and the middle pillar to fix the section of the railway bed that has been washed away. The units are also installing drainage pipes.

Regarding signal information, communication from Tuy Hoa station to Dieu Tri station has been temporarily restored to serve train operations; at the same time, automatic warning level crossings have been implemented to serve stone-carrying trains in response to the repair of the temporary bridge at Km 1136+800.

Source: https://baotintuc.vn/kinh-te/nganh-duong-sat-ngung-chay-45-chuyen-tau-va-chuyen-tai-3400-hanh-khach-bang-o-to-20251109130318002.htm


Comment (0)

No data
No data

Same tag

Same category

G-Dragon exploded with the audience during his performance in Vietnam
Female fan wears wedding dress to G-Dragon concert in Hung Yen
Fascinated by the beauty of Lo Lo Chai village in buckwheat flower season
Me Tri young rice is on fire, bustling with the pounding rhythm of the pestle for the new crop.

Same author

Heritage

Figure

Enterprise

Me Tri young rice is on fire, bustling with the pounding rhythm of the pestle for the new crop.

News

Political System

Destination

Product