Long Thanh Airport before welcoming the first flight

Long Thanh Airport is expected to welcome its first flight in December 2025. Currently, more than 14,000 people are working at full capacity to complete the items on this large construction site.

Báo Pháp Luật Việt NamBáo Pháp Luật Việt Nam24/11/2025

In late November 2025, the Long Thanh International Airport (Long Thanh Airport) construction site recorded an accelerated construction atmosphere. The investor, construction units and contractors are focusing on handling the large workload, striving to put the airport into operation with the first flight as planned.

Phase 1 includes a runway, a passenger terminal and ancillary infrastructure, with a capacity of 25 million passengers and 1.2 million tons of cargo per year.
Phase 1 includes a runway, a passenger terminal and ancillary infrastructure, with a capacity of 25 million passengers and 1.2 million tons of cargo per year.

According to Vietnam Airports Corporation (ACV), up to this point, the project component 3, essential works have completed 3 packages (fence; leveling and drainage; terminal pile construction) and are implementing construction of the remaining 12 packages.

The joint venture contractor continues to maintain "3 shifts, 4 crews" construction, speeding up progress to bring this national key project "to the finish line" before December 19.

The 3-phase 1 component project includes 2 runways, 1 passenger terminal and auxiliary items with a capacity of 25 million passengers/year, 1.2 million tons of cargo/year, with a total investment of more than VND 99,019 billion from ACV's capital. The project is expected to be basically completed in 2025 and put into commercial operation in the first half of 2026.

Over the past few days, engineers and workers have been installing a telescopic tube to lead passengers from the terminal to the aircraft parking lot.
Over the past few days, engineers and workers have been installing a telescopic tube to lead passengers from the terminal to the aircraft parking lot.

For package 4.6 (runway, taxiway, apron), the runway items have been basically completed and welcomed the first calibration flight on September 26. This is an important technical milestone to ensure the project is completed before December 19, 2025 and put into operation in the first half of 2026.

In package 4.7 (airport terminal parking lot), the joint venture has mobilized more than 1,780 engineers, workers and 521 pieces of equipment. Currently, the ground structure has been completed, the cement concrete volume has reached 79.4%, the drainage system has reached more than 93%. The ground service equipment tunnel is expected to be completed on November 30.

Mr. Nguyen Tien Viet, Deputy General Director of ACV, said that the items to be completed before December 19 include: the entire structure of the aircraft parking lot, the ground service equipment basement; drainage system, parking area lighting system, taxiways and parking area lighting system. The areas overlapping with underground technical infrastructure will be completed before March 2026.

Items such as the operator and security are entering the final stages of completion.
Items such as the operator and security are entering the final stages of completion.

For package 4.8 (internal port traffic and technical infrastructure), the construction units have completed more than 40.58%. Before December 19, the main trunk road connecting the terminal and the service road to the functional area of ​​​​phase I will be completed. The right viaduct branch connecting to the passenger terminal will also be completed within this time frame. At the end of November, the power supply system for the passenger terminal and the Air Traffic Control Tower will be completed, serving technical operations before December 19.

Package 4.9 (fuel supply system) will complete the building and auxiliary works before December 19; the fuel tank item will be completed before December 5. Some specialized equipment ordered from abroad will have mechanical installation completed by the end of March 2026.

In package 4.12 (second runway), the groundwork has been basically completed; crushed stone grading has reached 72.6%; cement concrete structure has reached 60.58%. The taxiway under construction has 63% of the groundwork, sand layer and crushed stone grading has reached 54%, cement concrete has reached 31.1%. The contractor will continue to mobilize human resources and equipment to basically complete the cement concrete items before December 19, in sync with the terminal's progress and prepare for exploitation in June 2026.

The runway has been completed, equipment installed and calibrated, and is qualified for operation.
The runway has been completed, equipment installed and calibrated, and is qualified for operation.

Package 5.10 (passenger terminal) currently employs 4,914 people and over 1,000 pieces of equipment. The architectural roof was basically completed in September for the wing area and will be completed in the central area before November 30. The steel structure of the telescopic bridge area was completed in October. The glass wall of the central area is expected to be completed before November 30.

The construction package for the traffic system connecting lines 1 and 2 is in the final stage. Line 1 was technically opened to traffic on April 30, 2025; Line 2 has completed the roadbed, foundation, and asphalt concrete pavement at 91%. The contractor is completing the traffic safety, tree, and lighting items and is expected to complete them in November.

ACV assessed that all the packages are being constructed simultaneously on the entire site, in the spirit of "overcoming the sun, overcoming the rain", "3 shifts, 4 crews". The contractor consortiums have mobilized nearly 14,000 personnel and more than 3,000 pieces of equipment, aiming to basically complete the project before December 19 and put it into commercial operation in early 2026.

In recent days, the weather has been unfavorable, the rainy season has come early and lasted long, greatly affecting underground items such as tunnels, drainage, and roadbeds. ACV has directed to adjust the construction plan and measures appropriately to ensure progress.

Regarding stone materials, the project is still short of about 520,000 m³ due to legal regulations. ACV recommends that Dong Nai province soon supplement the missing volume according to the contractor's needs.

According to Mr. Nguyen Tien Viet, despite many objective difficulties, the progress of the items is still closely following the direction of the Government, the Prime Minister and the management agency. All construction work is inspected, supervised and accepted according to current technical standards, ensuring the goal of basic completion before December 19, 2025 and commercial exploitation in the first half of 2026.

Source: https://baophapluat.vn/san-bay-long-thanh-truoc-thoi-diem-don-chuyen-bay-dau-tien.html


Comment (0)

No data
No data

Same tag

Same category

Traveling to "Miniature Sapa": Immerse yourself in the majestic and poetic beauty of Binh Lieu mountains and forests
Hanoi coffee shop turns into Europe, sprays artificial snow, attracts customers
The 'two-zero' life of people in the flooded area of ​​Khanh Hoa on the 5th day of flood prevention
4th time seeing Ba Den mountain clearly and rarely from Ho Chi Minh City

Same author

Heritage

Figure

Enterprise

Hanoi coffee shop turns into Europe, sprays artificial snow, attracts customers

News

Political System

Destination

Product