The project of connecting Provincial Road 342 with National Highway 279 has its starting point at Trai Me village and its ending point at Dong Dang village, Hoanh Bo ward. The project is nearly 11km long, with a planned design of 6 lanes. In the first phase, 4 lanes will be completed with a total investment of over 900 billion VND. Of which, the value of construction packages is nearly 513 billion VND, the rest is capital for site clearance, project management and reserve capital...
After more than 1.5 years of implementation, the construction has reached nearly 70% of the volume. Of which, all major bridges and cross-road drainage culverts have been basically completed. The excavation, filling, transportation and construction of the lower layer of the roadbed up to layer K95 has reached over 10km; the construction of the Km98 layer has reached about 6km and the crushed stone layer has reached over 2km. At the construction site, the contractors are focusing on filling the roadbed soil layers K95, K98, crushed stone, and constructing granular materials at the head of major bridges to prepare for the asphalt paving work.
Mr. Le Van Hieu, Site Commander, Technical Infrastructure Development and Construction Joint Stock Company, implementing the construction package at the beginning of the route connecting to Provincial Road 342, said: The contractor is concentrating on machinery and human resources to ensure continuous construction in 3 shifts. Shift 1 is from 6am to 11am, shift 2 is from 1pm to 5pm, and shift 3 is from 5pm to 10pm.

Taking advantage of the weather conditions during the dry season, along with mobilizing additional teams to speed up construction to compensate for the progress affected by heavy rain in the middle months of the year, the investor and contractors are also focusing on coordinating with local authorities to resolve the bottleneck of construction sites related to the remaining 10 households on the route. In order to do so, strive to basically cover the entire route with asphalt by the end of December and ensure the disbursement of 100% of the investment capital allocated for the project.
Mr. Vu Trung Thuc, Site Manager, Thanh Duong Company Limited said: Currently, the weather is very favorable for the construction of the roadbed and upper layers. If the entire route is clear, the construction will be very fast. With the view that working during the day is not enough, taking advantage of working at night, ensuring the human resources for construction in 3 shifts, 4 teams, the joint venture of contractors has made a detailed plan for each item to ensure the required goals set by the investor.

The completion of the route connecting Provincial Road 342 with National Highway 279 will contribute significantly to the completion of the traffic infrastructure connecting the province's mountainous communes with the province's expressway axis, thereby reducing the distance, promoting socio-economic development and improving the quality of people's lives.