According to a representative of Hai Phong Water Supply Joint Stock Company, by the end of November 14, the construction volume of the project to install a clean water supply pipeline system in Tan Minh commune (Hai Phong) invested by the company reached 80% of the plan.
With the current progress, Hai Phong Water Supply Joint Stock Company strives to complete the installation of water supply pipelines before November 20, 2025, more than 1 month ahead of schedule.
The project to install a clean water supply pipeline system in Tan Minh commune (Hai Phong) includes: investing in the main pipeline and the entire service pipeline network with a total length of 37.5 km. The total investment is more than 30.3 billion VND, construction will start in early October 2025.
.jpg)
According to the initial plan, the project will be constructed in about 120 days, of which the construction of the trunk line will be completed in December 2025, and the construction of the service transmission pipeline will be completed before the Lunar New Year of Binh Ngo. With the drastic participation of the local government and the support of the people, the construction progress of the trunk line has been accelerated.
After completing the main pipeline, Hai Phong Water Supply Joint Stock Company immediately started construction of the transmission and distribution pipeline system to hamlets and alleys and installed water meters to households.
.jpg)
To ensure the quality of water sources, before supplying water, Hai Phong Water Supply Joint Stock Company will disinfect the entire pipeline system; send technical teams to check water pressure, take samples to test water quality according to regulations.
According to design capacity, water plant pressure can supply water up to 5th floor of families.
PHAM CUONGSource: https://baohaiphong.vn/thi-cong-duong-truc-cap-nuoc-tai-xa-tan-minh-vuot-tien-do-hon-1-thang-526687.html