Resolutely handle difficulties related to site clearance (GPMB) to implement key projects of the province - This is the direction of comrade Trinh Viet Hung, alternate member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee, at the inspection of the progress of implementing key projects in the province, on November 21.
![]() |
Comrade Bui Van Luong, Secretary of the City Party Committee, Chairman of the People's Council of Pho Yen City, reported at the inspection session. |
Accompanying were comrades: Do Duc Cong, Member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Council; Bui Van Luong, Member of the Provincial Party Standing Committee, Secretary of the City Party Committee, Chairman of the People's Council of Pho Yen City; leaders of a number of relevant departments, branches, sectors and localities.
At the inspection, leaders of the Provincial Traffic Construction Investment Project Management Board, the Provincial Civil and Industrial Construction Investment Project Management Board, and leaders of relevant localities reported on the progress of project implementation.
![]() |
The Chairman of the Provincial People's Committee requested Dai Tu district to completely resolve the problems in site clearance work to speed up the construction progress of the connecting road connecting Thai Nguyen - Bac Giang - Vinh Phuc provinces through the district. |
Accordingly, for the connecting route connecting Thai Nguyen - Bac Giang - Vinh Phuc provinces, up to now, the Provincial Traffic Construction Investment Project Management Board has received the handover of 225.7/226ha of land, with 5/2,924 households still stuck. Of which, in Pho Yen city, 3/2,516 households are still stuck; Dai Tu district still has 02/408 households stuck.
Construction units are currently digging and filling 39/42.55km of land and deploying land filling and spreading crushed stone at some locations that meet construction conditions. In addition, they are organizing the construction of 11/11 bridges, 24/28 underpasses, 139/191 cross-culverts, 4/4 retaining wall locations and restoring irrigation ditches. The value of completed construction volume/contract value is 709/2,545 billion VND (reaching 28%); the accumulated value of disbursed and granted capital is 2,335/2,570 billion VND, reaching 91%.
For the Thai Nguyen Stadium Construction Project, the ground leveling project is being implemented on the area of 14.3 hectares that has been handed over; the ground leveling projects have been implemented including level I excavation reaching 90%, foundation excavation 88%, and foundation filling reaching over 90%; the main road foundation project, foundation excavation reaching 98%, road mold excavation reaching 80%; the mass pile driving of stand A has been completed and the construction of the foundation beams of the stand has been completed; for stands B, C, D, the foundation has been dug, pile heads have been broken, and concrete has been poured for the foundation...
![]() |
The Chairman of the Provincial People's Committee inspected the construction of the Office Building of the Bloc of Agencies of Thai Nguyen Province. |
The inspection shows that the province's key projects are being actively implemented, ensuring construction progress and capital disbursement. However, there are still some problems in site clearance work because some households have not yet handed over the land and technical infrastructure works (mainly power lines), causing difficulties in construction implementation, affecting the progress of the projects...
At the inspection, Chairman of the Provincial People's Committee Trinh Viet Hung acknowledged and highly appreciated the progress of construction and disbursement of public investment capital at the projects. He also requested relevant localities to continue to focus on thoroughly resolving difficulties and obstacles in site clearance work, combining propaganda and mobilization to gain people's consensus and agreement with the general policy.
For construction units, it is necessary to focus on human resources, materials, machinery and equipment to speed up construction progress of projects to ensure the plan.
![]() |
The working group inspected the implementation of the Glory Golf Course Project in Thanh Cong Commune (Pho Yen City). |
During the program, the delegation inspected the implementation of the Glory Golf Course Project in Thanh Cong Commune (Pho Yen City) and the Project to build the Headquarters of the Thai Nguyen Provincial Agencies.