Check the meter system in the area, ensure stable power supply in the dry season of 2025 |
According to the telegram, this year, the electricity load is forecast to grow by 12.2% (2.1% higher than in 2024), with the national maximum capacity reaching 54,510 MW (an increase of 11.3% compared to 2024).
To meet the electricity demand in the peak months of 2025 and the coming time, ministries, branches and localities must seriously and fully implement the Prime Minister's instructions on ensuring electricity supply. In particular, the Ministry of Industry and Trade , before May 10, 2025, shall issue a plan to implement the adjusted Power Plan VIII as a basis for implementing related projects. Strengthen inspection and supervision of the operation and urge the implementation of power source projects according to the plan. Direct the acceleration of the implementation of important national projects and key energy sector projects included in the plan...
Chairmen of People's Committees of provinces and centrally run cities shall direct local authorities to closely coordinate with central ministries, branches and relevant agencies to plan for reasonable water use for electricity production; make maximum use of wind and solar resources for electricity generation during peak periods. Effectively save electricity, especially in public lighting, lighting for advertising and outdoor decoration purposes; encourage the development of on-site power sources such as solar and wind power...
Upgrading the power grid system in Huong Thuy town ensures electricity supply by 2025 |
Mr. Nguyen Dai Phuc, Director of PC Hue, said that implementing the Prime Minister's Official Dispatch 49/CD-TTg, in addition to solutions for effective use and saving of electricity and plans to upgrade, repair and maintain the existing power grid infrastructure system in the locality, PC Hue focuses on investing in upgrading the medium and low voltage power grid in a number of districts, towns and cities with an estimated investment of about 365 billion VND.
That is the 110kV connection project after Chan May 220kV substation, the scale of investment in building 8 new 110kV transmission lines after Chan May 220kV substation (Phu Loc) with an investment of more than 54 billion VND, expected to be completed in 2025. The project to build Hue 5 110kV substation, phase 1 with the expected scale of installing 1 63MVA machine, along with 3.43km of single-circuit overhead line and 3.87km of single-circuit underground cable... contributes to ensuring stable power supply for the peak months of the dry season in the locality.
Source: https://huengaynay.vn/kinh-te/bao-dam-cung-ung-dien-cao-diem-mua-kho-153003.html