An Giang Provincial Party Secretary Le Hong Quang speaks at the meeting - Photo: VGP/LS
According to the report of the People's Committee of An Giang province, up to now, the total output of the 4 main construction packages has reached 48.8% (exceeding about 0.04% of the contract value). The total capital allocated at the beginning of 2025 is 3,449 billion VND. Up to the time of reporting, nearly 638 billion VND has been disbursed, reaching a rate of 18.5%...
At the meeting, members of the Steering Committee, leaders of relevant departments, branches, sectors, localities, contractors and construction units discussed and resolved difficulties and obstacles; proposed solutions to speed up construction progress, strive to complete component project 1 before June 30, 2026, ensuring quality as committed.
Concluding the meeting, An Giang Provincial Party Secretary Le Hong Quang commended the efforts of agencies, units, localities, contractors, engineers and workers to speed up construction progress beyond the set plan.
To complete the first phase of the project before June 30, 2026 in accordance with the direction of the Prime Minister , Mr. Le Hong Quang requested that members of the Steering Committee, the Working Group, and contractors continue to promote their sense of responsibility to the fullest extent, based on the assigned tasks, promptly and well implement the assigned key tasks.
The An Giang Provincial Project Management Board needs to urge contractors to increase machinery and equipment to organize construction to ensure the project's progress and quality. Regularly inspect and promptly remove difficulties and obstacles; promptly urge and issue written reminders to investors and construction units to ensure the project's progress.
The exploitation and supply of sand and stone must comply with the capacity prescribed by law, the Government 's resolution and the conclusion of the Prime Minister and Deputy Prime Minister. The Provincial People's Committee leads and directs the exploitation, supply and transportation to the construction site to ensure compliance with legal regulations and resolutely handle violations.
The An Giang Provincial Project Management Board monitors and urges contractors to promptly implement the construction of the resettlement area. The Department of Agriculture and Environment will promptly advise the Provincial People's Committee to allocate sand resources to build the resettlement area to soon stabilize the lives of affected households. In addition, it is necessary to promptly complete the process and procedures for adjusting and supplementing the investment scale, completing the intelligent traffic management system, rest stops, intersections and public service works in component project 1 and submit them to the competent authority for approval for synchronous implementation.
An Giang Provincial Party Secretary Le Hong Quang requested: Each member of the Steering Committee and the Working Group to continue to improve their responsibility in performing their tasks; proactively handle work according to assigned tasks, promptly report and ask for opinions on complicated, sensitive issues, and newly arising issues beyond their authority.
At the same time, it should be noted that the implementation process of all contents related to the above-mentioned project must ensure progress, quality, hygiene, environment, and assigned costs; the project implementation process must resolutely prevent corruption, waste, and group interests...
LS