Vietnam.vn - Nền tảng quảng bá Việt Nam

Binh Phuoc 1 Bridge built a temporary iron bridge for the 'genie' to raise it to 1.25m

The construction unit began erecting two temporary iron bridges at the first and last spans of Binh Phuoc 1 Bridge to allow motorbikes to pass when the "genie" raises the bridge's clearance.

Báo Tuổi TrẻBáo Tuổi Trẻ02/10/2025

Cầu Bình Phước 1 dựng cầu sắt tạm để ‘thần đèn’ nâng lên 1,25m - Ảnh 1.

The construction unit has begun erecting two temporary iron bridges at the first and last spans of Binh Phuoc 1 Bridge - Photo: CHAU TUAN

On October 2, the construction unit began erecting two temporary iron bridges at the first and last spans of Binh Phuoc 1 Bridge, National Highway 1 (HCMC) so that motorbikes can pass without being interrupted when the "genie" team officially raises the bridge's clearance.

A representative of the Department of Construction said that the work of raising Binh Trieu 1 Bridge to 1.08m had been completed. The remaining reinforcement and bracing items will be completed in November.

After Binh Trieu 1 bridge, the "genie" team continued to move their tools to Binh Phuoc 1 bridge to raise this bridge.

With the "bridge jacking" technique, engineers will install a hydraulic jack system under the bridge pillars and girders instead of dismantling or rebuilding. This system works synchronously to "push" the entire bridge, weighing thousands of tons, to the correct design height.

During construction, a temporary iron bridge was installed so that motorbikes could still travel normally (the first and last spans of the bridge were warped compared to the bridge approach road).

According to the plan, Binh Phuoc 1 Bridge will be raised by 1.25m, expected to be completed by the end of this year. Saigon Water Corporation is moving the D450 water pipeline running along the bridge to create a flat surface for construction.

The entire lifting system consists of more than 100 hydraulic jacks, each with a load capacity of 400 - 500 tons, synchronized through a central controller and monitored by computer, with a control error of less than 1mm.

Each time the bridge is raised, it is raised about 4cm. When it reaches the designed height, the bridge will be fixed with new bearings and pillars, the gap will be reinforced, then the jack will be "released", the load will be transferred to the new pillar and the load will be tested before being opened to traffic again.

Cầu Bình Phước 1 dựng cầu sắt tạm để ‘thần đèn’ nâng lên 1,25m - Ảnh 2.

Binh Phuoc Bridge 1 and 2 connecting National Highway 1 across Saigon River (connecting Thu Duc City and old District 12) has a lot of traffic every day.

Cầu Bình Phước 1 dựng cầu sắt tạm để ‘thần đèn’ nâng lên 1,25m - Ảnh 3.

Workers began installing steel stairs to access the bridge deck and girders.

Cầu Bình Phước 1 dựng cầu sắt tạm để ‘thần đèn’ nâng lên 1,25m - Ảnh 4.

Steel beams under Binh Phuoc 1 bridge will be reinforced.

Cầu Bình Phước 1 dựng cầu sắt tạm để ‘thần đèn’ nâng lên 1,25m - Ảnh 5.

Workers began installing a temporary iron bridge at the Binh Phuoc 1 bridgehead at noon on October 2.

Cầu Bình Phước 1 dựng cầu sắt tạm để ‘thần đèn’ nâng lên 1,25m - Ảnh 6.

Motorbikes will run over the temporary iron bridge during the time of raising Binh Phuoc 1 bridge.

Cầu Bình Phước 1 dựng cầu sắt tạm để ‘thần đèn’ nâng lên 1,25m - Ảnh 7.

Binh Phuoc 1 Bridge will be raised by 1.25m to ensure navigation clearance.

Cầu Bình Phước 1 dựng cầu sắt tạm để ‘thần đèn’ nâng lên 1,25m - Ảnh 10.

The bridge raising is expected to be completed by the end of this year.

Cầu Bình Phước 1 dựng cầu sắt tạm để ‘thần đèn’ nâng lên 1,25m - Ảnh 9.

Binh Phuoc 1 Bridge is much lower than Binh Phuoc 2 Bridge. Previously, this bridge was hit by a train, causing damage to the main span girder.

"Genie" continues to push Binh Phuoc 1 bridge

Ho Chi Minh City first applied this "magic lamp" technology in the Binh Trieu 1 bridge lifting project, helping to "push" the giant bridge weighing 11,000 tons to a height of 1.08m without having to demolish it. With Binh Phuoc 1 bridge, the technology continues to be applied, this time with a lifting height greater than 1.25m, to make it easier for ships to pass.

CHAU TUAN

Source: https://tuoitre.vn/cau-binh-phuoc-1-dung-cau-sat-tam-de-than-den-nang-len-1-25m-20251002130620766.htm


Comment (0)

No data
No data

Same tag

Same category

Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;