Safety assessment of Dau Tieng dam and reservoir

On June 2, at the Southern Irrigation Exploitation Company Limited, Dau Tieng - Phuoc Hoa Branch (Duong Minh Chau district), a meeting of the Advisory Council for Safety Assessment of Dau Tieng Dam and Reservoir took place.

Báo Tây NinhBáo Tây Ninh03/06/2025

Dau Tieng Lake flood discharge

Mr. Nguyen Tung Phong - Director of the Department of Management and Construction of Irrigation Works ( Ministry of Agriculture and Environment ) chaired the meeting. Attending were representatives of the Ministry of Agriculture and Environment, leaders of the Department of Agriculture and Environment of Tay Ninh, Long An, Binh Duong provinces, and related units.

Working group inspects flood discharge system of Dau Tieng Lake.

In 2024, the company will discharge 12 times through the spillway, with a discharge flow of 36 m3 -200 m3 /s, with a total discharge volume of about 1,447 million m3 . By the end of 2024, there will be 10 storms and tropical depressions active in the East Sea.

Members of the Advisory Council for Safety Assessment of Dau Tieng Dam and Reservoir.

Of these, 4 storms directly affected the mainland, causing widespread heavy rain, especially storm No. 4, which caused great damage to people and property. Heavy rains occurred in the Dau Tieng Lake basin. The average total rainfall in the basin in 2024 was 2,021 mm, 149 mm higher than in 2023.

At the meeting, experts and unit leaders assessed and advised on the safety level of dams, reservoirs, reservoir water storage plans and solutions to ensure safety of works and downstream dams.

Mr. Nguyen Tung Phong - Director of the Department of Management and Construction of Irrigation Works delivered a concluding speech at the meeting.

Concluding the meeting, Mr. Nguyen Tung Phong - Director of the Department of Management and Construction of Irrigation Works requested the Southern Irrigation Exploitation Company Limited to complete the repair and upgrade of the spillway before June 30, 2025 to ensure safe operation.

At the same time, review the current status of the project and the reservoir operation process to serve the multi-purpose of project safety, downstream and water supply, taking into account flood drainage plans; improve the quality of flow forecasts, flood discharge scenarios, including emergency situations; review the coordination regulations with localities in responding to and protecting the project...

Previously, the working group members inspected key areas of Dau Tieng Lake such as the main dam, floodgate system, dam system, etc.

Ocean

Source: https://baotayninh.vn/danh-gia-an-toan-dap-ho-chua-nuoc-dau-tieng-a190870.html