Minister of Industry and Trade Nguyen Hong Dien |
Speaking at the meeting, Minister Nguyen Hong Dien said that in order to carry out the tasks assigned by the Government , the Steering Committee will hold a meeting every two weeks to review progress, difficulties and obstacles, and propose solutions to accelerate key national energy projects. The Minister asked delegates to focus on the content with difficulties and obstacles; report on the work of resolving the tasks raised from the previous meeting.
The report of Vietnam Electricity Group (EVN) shows that the projects are currently being actively implemented and have achieved certain results. Specifically, the selection of contractors for projects importing electricity from Laos (500 kV Monsoon - Thanh My transmission line; 500 kV Thanh My MR TBA project; 220 kV Dak Ooc switching station project and 220 kV connecting line and 220 kV Nam Sum - Nong Cong transmission line project) has been completed, providing 100% of materials and equipment for the construction contractor.
Nhon Trach synchronous power grid projects including Nhon Trach 4 500kV line - Phu My - Nha Be branch have completed signing contracts for 05/05 packages, including construction, supply of steel poles, conductors and equipment (ET) for the line and transformer station. Nhon Trach 3 500kV line - Long Thanh 500kV substation has completed signing contracts for 05/06 packages, and the remaining package for supplying steel poles is expected to open for bidding on November 15, 2024. Nhon Trach Industrial Park 220kV transformer station and connection have completed signing contracts for 01/04 packages (packages are slow to be implemented because EVNNPT has not yet determined the time to hand over the site) ...; The Nhon Trach 3 220 kV Line project - My Xuan - Cat Lai branch has 4 bidding packages, so far bidding documents have been issued, and it is expected that in November 2024, contracts for 04/04 bidding packages will be completed.
For the 220 kV line of Long Thanh 500 kV Substation - High Technology, the investor has submitted a feasibility study report to the Ministry of Planning and Investment .
Online meeting with localities and electricity enterprises on power grid projects |
At the meeting, EVN and its units also reported on planning and land use plans; establishing and approving compensation and site clearance plans; and converting forest use purposes of the projects.
In particular, the project to import electricity from Laos has completed the planning and land use work; established and approved the compensation and site clearance plan (BTGPMB) and CMĐSDR and handed over the site to the construction contractor.
The Nhon Trach synchronous power grid projects have not yet carried out site clearance work because the Dong Nai Provincial People's Committee has not yet approved the planning and land use plans for the projects; at the same time, regulations on site clearance work according to the provisions of the 2024 Land Law have not been issued.
For the Lao Cai – Vinh Yen 500 kV transmission line project, the investment policy and CMĐSDR have been approved; the planning and land use plan have been updated. However, the work of preparing and approving the BTGPMB plan has not been carried out.
According to EVN representative, the projects are currently facing difficulties in site clearance due to many reasons, such as: some households are not eligible for compensation; some households do not receive compensation; obstruction of wire pulling; some locations are affected by forest trees falling on the foundation location... Some localities have not approved compensation and support plans for natural forest land of households. In particular, for the Nhon Trach synchronous power grid projects, there are common problems in approving planning, land use plans and site clearance.
Based on the report on difficulties of each specific project, Mr. Nguyen Anh Tuan - General Director of EVN proposed that the Steering Committee and localities pay attention and support investors to promptly resolve the above difficulties.
At the meeting, representatives of localities related to the projects reported quickly on the project implementation progress and proposed solutions to resolve difficulties of relevant ministries/sectors.