It is expected that Darahoa bus station will be built in the period of 2025 - 2028. In which, investment preparation and site clearance will be carried out until the fourth quarter of 2025. Construction completion time will not exceed 36 months from the date of land allocation.
This bus station has an area of 36.6 hectares in Da Sar commune, Lac Duong district, adjacent to Ward 12, Da Lat city with a total investment of more than 884 billion VND, serving about 817 50-seat passenger cars, 83 minibuses and more than 60 taxis with about 34,727 people including passengers, drivers and service staff.
The Prenn Pass parking lot is built on an area of 38 hectares, in Ward 3, Da Lat City and Hiep An Commune, Duc Trong District. The project has a total investment of about 1,000 billion VND. When put into operation, this parking lot will receive passenger cars to and from Da Lat City to the southern provinces and cities.
The above two projects are part of the plan to combat traffic congestion in Da Lat City until 2025 and vision to 2030.
Currently, passenger transport businesses to and from Da Lat City must register to operate at the Da Lat Interprovincial Bus Station. However, this is only a type 2 bus station and has been overloaded for many years. During rush hour, many passenger buses cannot enter the station to pick up and drop off passengers.
This is the main reason why many passenger transport businesses to and from Da Lat City arbitrarily set up stations, picking up and dropping off passengers right on routes in the center of Da Lat, causing public outrage.
Source: https://cand.com.vn/Giao-thong/gan-2-000-ty-dong-xay-2-ben-xe-chong-un-tac-cho-da-lat-i768441/