Urgent installation of steel poles on the 500kV Lao Cai - Vinh Yen line before the rainy season

Faced with the pressure of the approaching rainy season, contractors are speeding up the installation of steel poles on the 500kV Lao Cai - Vinh Yen transmission line, working day and night to keep up with the schedule and ensure the safety of this key national project.

Báo Lào CaiBáo Lào Cai03/06/2025

baolaocai-br_img-8145.jpg
A team of about 12 - 15 engineers and workers will be responsible for assembling 1 column position, and after completion, they will move to the new column position.
baolaocai-br_img-9452.jpg
To complete a power pole, workers must assemble hundreds of tons of steel structures.
baolaocai-br_img-0904.jpg
Progress pressure and huge workload are big challenges for workers and engineers.
baolaocai-br_img-0923.jpg
All are determined, strive to overcome difficulties, and work tirelessly.
baolaocai-br_dji-0098.jpg
Workers working at heights have to endure the scorching heat from steel bars scorched by the sun.
baolaocai-br_dji-0234.jpg
Construction workers at VT16 column location are completing the final stages.
baolaocai-br_img-8194.jpg
Every day of safe and effective work is the greatest joy for workers here.
baolaocai-br_dji-0858.jpg
Column VT24 of package 1 is one of the earliest completed column positions on the entire project route in Lao Cai province.
baolaocai-br_dji-0069.jpg
VT97 and VT98 poles on the banks of the Chay River, through Viet Tien commune, Bao Yen district, are pole locations at the end of the power line section passing through Lao Cai province.
baolaocai-br_dji-0212.jpg
According to the investor's report, the bidding packages in Lao Cai province are being implemented the fastest on the entire route.

Source: https://baolaocai.vn/gap-rut-lap-cot-thep-duong-day-500kv-lao-cai-vinh-yen-truoc-mua-mua-post402783.html