Vietnam.vn - Nền tảng quảng bá Việt Nam

Wire pulling, 500kV line, Hai Duong

Việt NamViệt Nam23/05/2024

anchor(1).jpg
This is the first stretch of wire to be pulled and is the longest stretch of the entire route in Hai Duong.

Power Construction Joint Stock Company 4 - Song Hong is the construction unit from column 276 to position 283 in the area of ​​Tan Hong and Thuc Khang communes (Binh Giang) with a length of nearly 3.1km. This is the longest anchorage of the line in Hai Duong. The contractor has mobilized maximum human and material resources to implement the construction with the determination to complete the wire pulling of the anchorage within 14 days...

The 500kV line 3 project from Quang Trach to Pho Noi, passing through Hai Duong, is nearly 31 km long, including 74 column foundation locations in 4 districts of Hai Duong: Ninh Giang, Gia Loc, Thanh Mien and Binh Giang. As of May 22, the contractor has completed all 74 column foundation locations, completed 47 locations, is constructing 15 locations, and has not yet been erected. According to the Prime Minister 's direction, the entire line must be completed by June 2024.

Up to this point, the 500kV line project, circuit 3 from Quang Trach to Pho Noi, has completed pulling 10/513 anchor spans and is currently pulling 7/513 anchor spans...

The 500 kV line project, circuit 3, Quang Trach - Pho Noi, once completed, will help reduce the load and avoid overloading of existing 500 kV lines, contributing to supplementing capacity from power sources in the North Central region to the load center in the Northern region...

THANH HOA

Source

Comment (0)

No data
No data

Same tag

Same category

Enduring journey on the rocky plateau
Cat Ba - Symphony of Summer
Find your own Northwest
Wildlife on Cat Ba Island

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product