Many construction projects have been halted due to land clearance issues.

QTO - The Basic Infrastructure Project for Comprehensive Development of Nghe An, Ha Tinh, Quang Binh and Quang Tri Provinces - Quang Binh Province Sub-project (BIIG2 Quang Binh Project) currently has 3 bidding packages where land clearance has not been completed, therefore construction work has to be temporarily suspended.

Báo Quảng TrịBáo Quảng Trị17/12/2025

Land clearance issues persist in the bidding package for the road connecting the National Highway 1A bypass to the eastern branch of the Ho Chi Minh Highway. Photo: B.T
Land clearance issues persist in the bidding package for the road connecting the National Highway 1A bypass to the eastern branch of the Ho Chi Minh Highway - Photo: BT

Specifically, in the bidding package for the road connecting the National Highway 1 bypass to the eastern branch of the Ho Chi Minh Highway, there are still 3 households that disagree with receiving compensation for land clearance due to concerns that the compensation price is too low. In particular, one household, during the land clearance process, requested a change from monetary compensation to resettlement, prolonging the implementation time (the planned resettlement area is not expected to be completed until March 2026).

For the Dinh Muoi Tourist Road project, there is still one household that is being persuaded to accept compensation in the form of land (the household is requesting compensation in the form of land).

Regarding the road project from Loc Ninh commune to the Northwest Dong Hoi Industrial Zone, there are still 19 households that have not been compensated. To date, successful efforts have been made to persuade 9 households to agree to the compensation plan and are considering handing over the land to the contractor for construction. The remaining 10 households have not agreed, including 2 households who have not agreed to the resettlement plan; 6 households who have not agreed to the compensation and support plan; 1 household who has not agreed to the land survey; and 1 household that has filed a complaint.

Photo: B.T
Due to land clearance issues, one construction package has to be temporarily suspended - Photo: BT

Currently, the People's Committees of Dong Son and Dong Thuan wards and Quang Ninh commune, along with the Project Management Boards for Investment, Construction and Land Development in Dong Hoi and Quang Ninh, are urgently completing the compensation plan and submitting it to the competent authorities for appraisal and approval in order to organize payments to households that have agreed to the compensation plan before December 31, 2025.

At the same time, continue to persuade households that have not yet agreed to the plan; urgently complete the dossiers and submit them for appraisal and approval as soon as the 60-day persuasion period ends as stipulated. In case households still refuse to accept the compensation, relevant agencies and units will implement the land reclamation enforcement process as prescribed.

Due to land clearance issues, contractors working on the following projects have completed 90% of the construction: the road connecting the National Highway 1 bypass to the eastern branch of the Ho Chi Minh Highway; the Dinh Muoi tourist road (75%); and the road from Loc Ninh commune to the Northwest Dong Hoi Industrial Zone (85%). They are waiting for the remaining land to be handed over in order to complete the remaining projects.

Quang Thanh

Source: https://baoquangtri.vn/kinh-te/202512/nhieu-goi-thau-dung-thi-cong-do-dang-vuong-giai-phong-mat-bang-1ec670f/


Comment (0)

Please leave a comment to share your feelings!

Same category

A close-up view of the workshop making the LED star for Notre Dame Cathedral.
The 8-meter-tall Christmas star illuminating Notre Dame Cathedral in Ho Chi Minh City is particularly striking.
Huynh Nhu makes history at the SEA Games: A record that will be very difficult to break.
The stunning church on Highway 51 lit up for Christmas, attracting the attention of everyone passing by.

Same author

Heritage

Figure

Enterprise

Farmers in Sa Dec flower village are busy tending to their flowers in preparation for the Festival and Tet (Lunar New Year) 2026.

News

Political System

Destination

Product