Updated data on the morning of June 20 from Vietnam Electricity (EVN) and the National Power System Dispatch Center (A0) showed that on June 19, the load of the entire power system increased compared to June 18, reaching about 809.5 million kWh.
Of which the North is estimated at about 382.9 million kWh, the Central region is about 77.6 million kWh (increased), and the South is about 348.4 million kWh.
The national power system peak capacity (Pmax) reached 39,504.2 MW at 2:30 p.m., of which the North/Central/South regions (Pmax/time) were: 17,312.9 MW (at 3:30 p.m.), 4,071 MW (at 2:30 p.m.), 18,240.2 MW (2:30 p.m.).
On June 19, the load of the entire power system increased compared to the previous day. Illustration photo: Ministry of Industry and Trade |
Regarding power mobilization, on June 19, 2023, the total output mobilized from hydropower increased sharply; reaching about 170.5 million kWh (of which hydropower in the North mobilized 59.9 million kWh); coal-fired thermal power mobilized 430.9 million kWh (Northern 269.2 million kWh); gas turbines mobilized 92.5 million kWh. No need to mobilize oil power sources. Renewable energy sources of all kinds reached 108.8 million kWh.
Regarding the transitional renewable energy projects, as of June 19, there were 55 projects with a total capacity of 3,052 MW submitted to the Ministry of Industry and Trade; of which 51 projects have signed additional temporary power purchase contracts. There are 10 factories (the whole factory or part of the factory) with a total capacity of 455 MW that have been put into commercial operation, 4 factories are undergoing testing and 12 factories are completing testing and waiting for commercial operation.
EVN representative said that the coal fuel source for electricity production is guaranteed. However, the problems of the generators are still happening. Specifically, the long-term problem is about 2,100 MW, the short-term problem is 880 MW. Currently, the factories are trying to handle the problem, it is expected that by June 21, the Nghi Son 1 generator unit S1 and the problem part of the Mong Duong 1 Thermal Power Plant unit 1 will be back on the grid; on June 23, the Thang Long Thermal Power Plant unit S1 will be fixed.
According to the report, large hydroelectric reservoirs in the North are above the dead water level but are still facing difficulties. The total capacity of the plants (Son La, Lai Chau , Ban Chat, Huoi Quang, Tuyen Quang, Thac Ba, Hua Na, Ban Ve,...) reaches nearly 5,000 MW. Currently, the reservoirs are still accumulating more water.
Currently, the Ministry of Industry and Trade and Vietnam Electricity Group are continuing to direct relevant units to increase power sources and flexibly operate reservoirs in the context of difficulties in hydropower reservoirs; urging thermal power plants to prioritize handling incidents in generators; ensuring coal and gas supply for power generation; actively supplementing renewable energy sources for the system; enhancing safe operation of the Central - Northern transmission system; and at the same time, promoting propaganda work to implement the Prime Minister 's Directive on electricity saving...
MR. NGOC