Efforts to complete the Tam Hoa Main Road project on schedule

DNO - The Tam Hoa main road project connecting National Highway 1 to Vo Chi Cong Street and DT.613B is a key project in the South of Da Nang City. However, this project is facing obstacles in terms of construction site and has to postpone the completion date to the end of 2025.

Báo Đà NẵngBáo Đà Nẵng13/08/2025

Tam Hoa 1 Road
Up to now, the project has handed over 3.3/4.8km of land and the construction unit has deployed on this land area. Photo: HOANG DAO

The Tam Hoa Main Road Project connecting National Highway 1 to Vo Chi Cong Street and DT.613B has a length of 4.8km. The starting point of the project is from the intersection of National Highway 1 at Km1006+198 and ends at the intersection with DT.613B at Km35+750 (Thanh Nien Coastal Road). The total investment capital is 646 billion VND from the central budget and local budget.

Tam Hoa 8 Road
The Truong Giang Bridge project has completed abutments M1, T3, T4, T5, T6, T7, the main span and cast Super T approach span girders. Photo: HOANG DAO

The project started on April 26, 2023 and was expected to be completed on April 25, 2025, but due to site clearance problems, the People's Committee of Quang Nam province (old) agreed to extend the deadline to December 31, 2025.

To date, the project has handed over 3.3/4.8km of construction site. Including the site of M1 pier, T1 to T7 pier of Truong Giang bridge; T2 to T6 pier, M2 pier of Cho river bridge; 0.6km of the route paid in advance for construction of public roads and 2.2km of the route through the forest land area handed over in March 2025.

Tam Hoa 5 Road

Tam Hoa 7 Road
Despite the hot weather, workers of Thai Son Traffic Construction Joint Stock Company continue to construct the T1 and T2 pillars of Truong Giang Bridge. Photo: HOANG DAO
Tam Hoa 9 Road
Cho River Bridge has completed piers T2, T3, T4, T5, pier M2 and is implementing pier T6, casting approach girder I33. Photo: HOANG DAO
Tam Hoa 2 Road
For the road section, the construction unit is carrying out embankment construction for 2.2/4.1km. Photo: HOANG DAO
Tam Hoa 4 Road
The value of the volume of work performed so far is 249.3/516 billion VND (reaching about 48.3% of the contract value). Photo: HOANG DAO
Tam Hoa 6 Road
Photo: HOANG DAO

There are still 271 plots of land that have not completed the procedures for establishing and approving compensation, support and resettlement plans to hand over the construction site. This has caused the construction progress to be slow and not as expected. To overcome the difficulties, on the afternoon of August 13, the Quang Nam Provincial Project Management Board for Construction Investment held a meeting with the People's Committee of Tam Anh Commune, Branch 11 of the Da Nang City Land Fund Development Center to soon clear the entire route for project construction.

[ VIDEO ] - Construction site of Tam Hoa main road project connecting from National Highway 1 to Vo Chi Cong Street and DT.613B:

Source: https://baodanang.vn/no-luc-thi-cong-dung-tien-do-du-an-duong-truc-chinh-tam-hoa-3299305.html


Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;