The project to build a grade-separated interchange between Ring Road 3.5 and Thang Long Avenue, with a total investment of nearly VND2,400 billion, has officially entered the tunneling phase after more than 6 months of implementation. This key project is expected to complete the traffic infrastructure network in the West of Hanoi, resolve bottlenecks and promote socio -economic development in the area.

Urgent construction progress
According to records at the end of October, the project site in An Khanh commune is operating at full capacity. Dozens of heavy machinery such as excavators, pile drilling machines, tower cranes and a large number of workers are working continuously to ensure progress. Many important items have gradually taken shape, especially the construction of steel structures for branch bridges and the start of tunnel excavation.

Engineering design of modern intersections
The complex design includes a direct tunnel and a turbine-shaped overpass system to effectively divide traffic flow and minimize conflicts between vehicles.
Underpass category
The underpass is built in the direction of Le Trong Tan Street extension (currently Hoang Tung Street) connecting with National Highway 32. The tunnel has a total length of 975m, with a scale of 4 lanes. The tunnel structure includes:
- Closed tunnel: 150m long, underground under Thang Long Boulevard.
- Open tunnel: 157.5m long on Hoang Tung street side.
- Retaining wall: Total length 220m.

Overpass and turbine branches
The project has 4 turbine bridge branches using prestressed reinforced concrete slab girders, with a total length of 2,346m. Each bridge branch is 8.8m wide, with 2 lanes for motor vehicles. In addition, auxiliary items such as wheel barriers with a total length of 619m are also being deployed synchronously.

Project overview
The Ring Road 3.5 - Thang Long Avenue Interchange Project was approved by the Hanoi People's Committee with a total investment of about 2,384 billion VND. The investor is the Hanoi City Civil Works Construction Investment Project Management Board. According to the plan, the construction period is expected to last about 1,000 days (more than 3 years), in the implementation period of 2022-2026.

Source: https://baolamdong.vn/nut-giao-2400-ty-phia-tay-ha-noi-bat-dau-dao-ham-399008.html

![[Photo] The Third Patriotic Emulation Congress of the Central Internal Affairs Commission](https://vphoto.vietnam.vn/thumb/1200x675/vietnam/resource/IMAGE/2025/10/30/1761831176178_dh-thi-dua-yeu-nuoc-5076-2710-jpg.webp)

![[Photo] General Secretary To Lam attends the Vietnam-UK High-Level Economic Conference](https://vphoto.vietnam.vn/thumb/1200x675/vietnam/resource/IMAGE/2025/10/30/1761825773922_anh-1-3371-jpg.webp)
![[Photo] Prime Minister Pham Minh Chinh attends the 5th National Press Awards Ceremony on preventing and combating corruption, waste and negativity](https://vphoto.vietnam.vn/thumb/1200x675/vietnam/resource/IMAGE/2025/10/31/1761881588160_dsc-8359-jpg.webp)











































































Comment (0)