On the morning of May 22, a working delegation of Nghe An Provincial People's Committee led by Mr. Phung Thanh Vinh - Vice Chairman of the Provincial People's Committee, inspected the construction sites and projects in Ky Son district. Accompanying them were representatives of the Departments of Ethnic Minorities and Religion, Agriculture and Environment, Construction, Industry and Trade, and Finance.

Accordingly, the delegation of the Provincial People's Committee inspected the Electricity Project for villages and residential areas without national grid electricity in Ky Son district, invested by the People's Committee of Ky Son district, and the Inter-commune Road Project from Khe Loi bridge intersection, Ta Ca commune to block 4, Muong Xen town, invested by the People's Committee of Ky Son district.

According to the report of the People's Committee of Ky Son district, the Inter-commune Road Project from Khe Loi Bridge intersection, Ta Ca commune to Block 4, Muong Xen town, has a total approved investment of 35 billion VND. As of May 21, the work volume has reached 80%, disbursed more than 21 billion VND, reaching 60.04% of the plan.
Ky Son district is expected to organize the completion acceptance and handover for use by June 10, 2025.

The project of electricity works for villages and residential areas without national grid electricity in Ky Son district has a total approved investment of 92.77 billion VND. Up to now, the project has achieved about 40% of the volume, disbursed nearly 16 billion VND, reaching 16.97% of the plan.
.jpg)
Working with the People's Committee of Ky Son district, Vice Chairman of the Provincial People's Committee Phung Thanh Vinh assessed that during the implementation of the projects, there have been many efforts and the results achieved are quite positive.

To keep up with the project's progress, Vice Chairman of the Provincial People's Committee Phung Thanh Vinh assigned the People's Committee of Ky Son district to overcome all difficulties, focus on directing these two projects as well as other projects in the district to prepare human resources and materials well to grasp, have specific plans for each stage to speed up the construction progress and disburse public investment capital to meet the assigned plan.
Regarding construction quality, it is necessary to pay attention to the quality of input materials to ensure specifications and standards, and to assess the quality of all types of materials.
Departments, branches and sectors proactively grasp problems and difficulties to promptly resolve them; in which, the Department of Agriculture and Environment guides the district in finding sand and stone mines...
Source: https://baonghean.vn/pho-chu-tich-ubnd-tinh-nghe-an-phung-thanh-vinh-kiem-tra-cac-du-an-tren-dia-ban-huyen-ky-son-10297956.html