Recently, the project of Maintenance and Repair of Unit 1 at Thai Binh 1 Thermal Power Plant (capacity 300MW) with the work items of inspection and maintenance of steam turbines, generators and auxiliary equipment has been successfully implemented by PTSC Thanh Hoa. With the goal of successfully implementing the project, ensuring Safety - Quality - Progress, meeting customer requirements, despite the urgent implementation time with high complexity, the collective of workers in the Operation and Maintenance Project Management Board (O&M) of PTSC Thanh Hoa has shown great determination, arranging and organizing the implementation of the project professionally right from the start.
Turbine Generator – 300MW
Valve and bearing cleaning work
Through the project implementation period from October 14, 2024 to November 17, 2024 with many difficulties and challenges, the O&M Project Management Board was always confident and coordinated smoothly in the implementation stage with the support of Thai Binh 1 Thermal Power Plant and Soundton customer. Finally, PTSC Thanh Hoa successfully implemented the project and was accepted after a 72-hour continuous full-load power generation test run, according to the plant's plan.
Remove RSV valve for maintenance
The success in performing maintenance and repair of the 300MW turbine generator and auxiliary equipment for the thermal power plant has marked an important milestone and affirmed the prestige, capacity and experience for PTSC Thanh Hoa to continue to participate more in maintenance and repair work for thermal power plants in the coming time.
Nguyen Thi Nhung
Source: https://www.ptsc.com.vn/tin-tuc/tin-ptsc-1/san-xuat-kinh-doanh/ptsc-thanh-hoa-trien-khai-thanh-cong-du-an-trung-tu-bao-dung-sua-chua-to-may-s1--nha-may-nhet-dien-thai-binh-1
Comment (0)