Highly determined to open the Hoa Lien-Tuy Loan expressway on August 19

(Chinhphu.vn) - The Ho Chi Minh Road Project Management Board has directed functional units and contractors to re-establish progress and high determination for the goal of opening the Hoa Lien - Tuy Loan expressway on August 19; completing the entire project by November 2025.

Báo Chính PhủBáo Chính Phủ15/05/2025

Quyết tâm cao độ thông tuyến cao tốc Hòa Liên-Túy Loan vào 19/8- Ảnh 1.

Hoa Lien - Tuy Loan Expressway is expected to open to technical traffic on August 19 - Photo: Construction Newspaper

Deputy Minister of Construction Nguyen Viet Hung recently inspected the construction site of the Hoa Lien - Tuy Loan expressway, the section passing through Hoa Vang district, Da Nang city.

Target to open route on August 19

Mr. Le Thanh Binh, Deputy Director of the Ho Chi Minh Road Project Management Board, said that the locality has handed over all the cleared land to the main highway. Regarding the service road and cross-road, there are still 5 households that have not relocated their houses and structures. The Board and the locality are coordinating to resolve the issue.

Currently, the project progress has reached about 60% of the plan, focusing on the following items: digging the roadbed; filling K95, K98; constructing crushed stone, asphalt concrete of all kinds... basically meeting the requirements.

Implementing the direction of the Prime Minister , the Ministry of Construction and the Ho Chi Minh Road Project Management Board have directed functional units and contractors to re-establish progress and high determination for the goal of opening this expressway on August 19; completing the entire project by November 2025.

According to Mr. Ta Gia Manh Hung, Director of the Hoa Lien - Tuy Loan Expressway Project Management Board, the remaining construction volume on the main route is more than 200 billion VND. With 3 paving lines, contractors strive to achieve a minimum daily output of 3-4 billion VND. "We have asked contractors to create a progress chart and sign a commitment to strictly control during the peak period of the finish line," Mr. Hung informed.

After inspecting the construction site, Deputy Minister Nguyen Viet Hung noted that the project is entering its peak phase, preparing to reach the finish line, and the obstacles in site clearance and basic materials have been resolved by Da Nang City. The Ho Chi Minh Road Project Management Board and contractors need to continue to promote the spirit of "overcoming the sun and overcoming the rain", "working 3 shifts and 4 shifts" to closely follow the progress, control the quality of the project, and ensure the goal of opening the route on August 19, to celebrate the 80th anniversary of National Day and the 80th anniversary of the tradition of the transport sector.

Regarding the remaining problems regarding the site for the frontage road, the Deputy Minister requested the investor and contractor to proactively coordinate with the locality to resolve the issue in May and complete the frontage road in November.

The Hoa Lien - Tuy Loan expressway project is 11.47km long, passing through Hoa Lien, Hoa Nhon, and Hoa Son communes of Hoa Vang district, Da Nang city, with a total investment of more than 2,100 billion VND.

The project is invested by the Ho Chi Minh Road Project Management Board, started in September 2023, and completed according to the contract in November 2025.

The project has 1 construction package constructed by the Joint Venture of Truong Son Construction Corporation - CTGT 5-CTCP Construction Corporation - 17 LLC.

Phan Trang


Source: https://baochinhphu.vn/quyet-tam-cao-do-thong-tuyen-cao-toc-hoa-lien-tuy-loan-vao-19-8-102250515140454169.htm


Comment (0)

No data
No data

Same category

Picturesque 'infinity' beach in Central Vietnam, popular on social networks
Follow the sun
Come to Sapa to immerse yourself in the world of roses
Wildlife on Cat Ba Island

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product