After nearly a year of construction, the Hoang Sa - Doc Soi road project ( Quang Ngai ) with a total investment capital of 3,500 billion VND has only disbursed about 6% due to land acquisition problems.
After nearly a year of construction, the 3,500 billion VND project in Quang Ngai has only disbursed about 6%.
After nearly a year of construction, the Hoang Sa - Doc Soi road project (Quang Ngai) with a total investment capital of 3,500 billion VND has only disbursed about 6% due to land acquisition problems.
New disbursement of about 6%
The Hoang Sa - Doc Soi road construction investment project has a total length of 26.88 km, with a total investment of 3,500 billion VND, invested by the Provincial Traffic Construction Investment Project Management Board. The project started in December 2023 and is expected to be completed in 2025.
After 1 year of construction, the project has only disbursed about 6%. |
According to the report of the Quang Ngai Traffic Construction Investment Project Management Board, up to now, the Hoang Sa - Doc Soi road project has only disbursed 135 billion VND out of the total construction package value of 2,322 billion VND, equivalent to 6% of the contract value.
According to the reporter's observations at the Hoang Sa - Doc Soi road project, some locations have handed over clean land, the contractor has arranged human resources and equipment for construction, but there are also many places where construction is quiet.
For example, in Tinh An commune (Quang Ngai city), only a few workers and machinery are standing still. Along the main route through Quang Ngai city, Son Tinh and Binh Son, construction work is being affected due to site clearance problems.
The contractor representative said that due to limited construction sites, the unit focused on the bridge items and some sections that had cleared land. Hopefully, the investor will soon hand over more land to speed up the progress.
The investor also admitted that the project progress was slower than planned. The reason was due to problems in the implementation process, of which the biggest problem was related to compensation and site clearance.
To date, localities have only handed over more than 32/164ha of land, reaching nearly 20% of the total land area that needs to be recovered for project construction. Of which, Binh Son district handed over 20.82/105.59ha; Son Tinh district handed over 0.5/15.89ha and Quang Ngai city handed over 10.89/43.04ha.
Urgently remove obstacles
Faced with this situation, Quang Ngai provincial leaders inspected the scene and had many working sessions with investors and localities to resolve difficulties.
At the meetings, the leaders of Quang Ngai province pointed out that the main problem is due to many difficulties in compensation, site clearance, and resettlement. The reason is that the 2024 Land Law has just been issued, and localities have not yet completed the work of approving specific land prices.
Hoang Sa - Doc Soi road project (Quang Ngai) has a total investment capital of 3,500 billion. |
The Quang Ngai Traffic Construction Investment Project Management Board said that to ensure project progress, localities where the project passes through urgently approve specific land prices according to the provisions of the 2024 Land Law, as a basis for approving compensation plans, relocating people and resettlement to have clean land to hand over to the construction contractor.
To remove the obstacles, Mr. Ngo Van Dung, Director of the Quang Ngai Traffic Construction Investment Project Management Board, requested the Quang Ngai Provincial People's Committee to direct the Department of Natural Resources and Environment to continue construction and support construction units to soon complete the procedures for granting sand mining licenses.
At the same time, Son Tinh and Binh Son districts and Quang Ngai city need to speed up the approval of specific land prices and completely resolve problems related to resettlement areas.