On June 1, Shock Team 2 consisting of 17 officers, engineers and workers of Phu Yen Power Company set off to support the construction of the 500kV Line 3 project from Quang Trach (Quang Binh province) to Pho Noi ( Hung Yen province). Previously, the company's Shock Team 1 consisting of 14 officers, engineers and workers also set off and is currently present at the construction site.
According to Phu Yen Electricity Company, to carry out this task, 2 shock teams of the unit will participate in erecting 500kV poles, bringing materials and equipment to the line positions... of 2 pole positions in Dien Chau district, Nghe An province, construction time from May 31 to June 30.
It is known that the 500kV Line 3 project from Quang Trach to Pho Noi has a total length of about 519km, passing through 211 communes and wards of 43 districts and towns in 9 provinces: Quang Binh, Ha Tinh , Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh, Hai Duong, Hung Yen. The total number of column foundations to be constructed is 1,179 column foundations, with a total investment of more than 22,000 billion VND.
This project aims to enhance the capacity of the 500kV North-Central transmission grid, helping to increase the transmission capacity between the Central and Northern regions from the current 2,200MW to about 5,000MW, contributing to ensuring power supply for the North; helping to improve the reliability of power supply, contributing to increasing power transmission from power sources in the North Central region to the load center in the Northern region.
Narcissus
Source
Comment (0)