Bien Hoa - Vung Tau Expressway takes shape after more than 8 months of construction

Báo Giao thôngBáo Giao thông11/03/2024


Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 1.

The Bien Hoa - Vung Tau Expressway project, consisting of three component projects passing through Dong Nai and Ba Ria - Vung Tau provinces, was simultaneously started in June 2023. After more than 8 months of launching, there have been many differences along the entire route.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 2.

In Ba Ria - Vung Tau province, thanks to good site clearance work, construction took place quickly and the road has taken shape.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 3.

The engineers working on the expressway said they were quite surprised by the speed of land clearance in Ba Ria - Vung Tau province. Thanks to that, the contractors quickly deployed construction teams for both the bridge and road sections on the route.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 4.

“From the vast forests, the main road has now been opened and construction has been carried out from beginning to end. Some sections have been graded with crushed stone, stone spread, and rolled… Trucks carrying construction materials can now move smoothly. Observing through a flycam, one can see that the road has taken shape and is very beautiful,” said an engineer.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 5.

According to engineers, due to the long rainy season in 2023, construction work on component 3 of the project basically started in November. Therefore, the consortium of contractors mobilized 3 shifts to speed up the progress.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 6.

The progress and shape of the project changes day by day, week by week and month by month. The difference is clearly shown in each stage.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 7.

In particular, from the first section of component project 3 (Phu My town) adjacent to component project 2 section (Long Thanh district, Dong Nai ), the 2-door residential underpass is also being implemented. Workers and engineers work together in the sun to ensure the progress of this item.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 8.

The road section from the beginning of component 3 project to the construction area of ​​Suoi Nhum bridge and many other sections through Phu My town and Ba Ria city have also taken shape, many sections have been graded with crushed stone and rolled foundation...

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 9.

The bridges on the route are also being deployed with bored piles, beam casting, etc.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 10.

According to the Cai Mep - Thi Vai Port Area Traffic Project Management Board (investor), the Bien Hoa - Vung Tau Expressway Component 3 project, this project passes through Ba Ria - Vung Tau province, is 19.5km long. The project has a construction package (package 11 - construction and equipment) constructed by a consortium of contractors: Son Hai Group Co., Ltd. - Hoa Binh 479 Joint Stock Company - 703 Investment and Construction Joint Stock Company.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 11.

The construction value of the contract is 1,847 billion VND and the contract implementation time is 806 days, equivalent to more than 2 years. Expected completion in September 2025 (3 months ahead of schedule).

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 12.

To implement the project, Ba Ria - Vung Tau must reclaim more than 137.52 hectares of land from 1,215 households and organizations. To date, the total approved compensation budget is over VND 2,719.14 billion for 1,209 households and organizations. The total budget paid is over VND 2,620.82 billion. To date, the total area of ​​households that have signed the land handover minutes is 135/137 hectares, reaching over 98%. Some households in Phu My town have not yet handed over the land, so the locality is continuing to mobilize.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 13.

The Project Management Board said that so far, there are 11 bridges and 1 underpass along the entire route. The joint venture of contractors mobilized 350 equipment and 500 personnel to deploy 15 construction teams. The completed volume reached 178 bored piles, 45 girders and 2,021m3 of concrete for the bridge base and abutment body.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 14.

Filling the K0.95, K1.02 roadbed, service road, right branch road at the National Highway 56 intersection and constructing crushed stone aggregate. The cumulative construction value of component project 3 to date has reached about 240 billion VND, equivalent to 13%.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 15.

The Cai Mep - Thi Vai Port Area Traffic Project Management Board said that in the coming time, contractors will continue to simultaneously carry out the work of filling the roadbed, filling the public road, and drainage culverts; speed up the implementation of additional overpasses at Km42+167, residential underpasses, and complete site clearance for the entire project.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 16.

“The contractors will mobilize workers in 3 shifts and 4 crews to complete the project’s road embankment and drainage works before April 30; regularly evaluate the construction progress according to the Gantt chart,” said a representative of the Cai Mep - Thi Vai Port Traffic Project Management Board.

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 17.

While the expressway section through Ba Ria - Vung Tau has been formed and graded with crushed stone, the Dong Nai side is still just a green area with bushes and houses stretching out. The land clearance work in Dong Nai is slow due to the struggle to count ownerless land and land that has been transferred back and forth...

Cao tốc Biên Hòa - Vũng Tàu nên vóc nên hình sau hơn 8 tháng thi công- Ảnh 18.

The Bien Hoa - Vung Tau Expressway Project has a total length of 53.7km (34.2km through Dong Nai province, 19.5km through Ba Ria - Vung Tau province). Of which, component project 1 is 16km long, with Dong Nai Provincial People's Committee as the managing agency, with a total investment of 6,012 billion VND. Component project 2 is more than 18km long, with the Ministry of Transport as the managing agency, with a total investment of 6,852 billion VND. Component project 3 is about 19.5km long, with Ba Ria - Vung Tau Provincial People's Committee as the managing agency.



Source

Comment (0)

No data
No data

Same tag

Same category

Enjoy the top fireworks at the opening night of the 2025 Da Nang International Fireworks Festival
Da Nang International Fireworks Festival 2025 (DIFF 2025) is the longest in history
Hundreds of colorful offering trays sold on the occasion of the Duanwu Festival
Ninh Thuan's infinity beach is most beautiful until the end of June, don't miss it!

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product