Vung Ang - Bung Expressway unlikely to "finish" by the end of June

(Baohatinh.vn) - Despite many efforts, the Vung Ang - Bung expressway through Ha Tinh and Quang Tri (formerly Quang Binh) is unlikely to be open to traffic on June 30.

Báo Hà TĩnhBáo Hà Tĩnh20/06/2025

bqbht_br_cao-toc-vung-ang-bung-15c.jpg
bqbht_br_cao-toc-vung-ang-bung-3.jpg
These days, taking advantage of favorable weather, Hoa Binh 479 Joint Stock Company is focusing on the construction of Bridge No. 1 of the Vung Ang - Bung Expressway project, Ha Tinh section. Bridge No. 1 is 942 m long, has 22 spans, crosses the valley terrain in Ky Hoa commune, Ky Anh town, and was officially started in February 2023.
bqbht_br_cao-toc-vung-ang-bung-17b.jpg
After nearly two and a half years of construction on difficult terrain and heavily affected by the weather, the contractor has completed the installation of 19 bridge spans.
bqbht_br_cao-toc-vung-ang-bung-13d.jpg
bqbht_br_cao-toc-vung-ang-bung-13c.jpg
The contractor is working hard to connect the last two spans of the bridge. At the same time, they are focusing on completing the railing system and continuous thermal panels before proceeding to asphalt concrete paving the bridge deck. The construction volume of bridge No. 1 has reached 93% of the plan so far.
bqbht_br_cao-toc-vung-ang-bung-2f.jpg
bqbht_br_cao-toc-vung-ang-bung-4.jpg
Despite all the efforts, due to the large remaining construction volume, bridge item number 1 will almost certainly not be completed by June 30.
bqbht_br_cao-toc-vung-ang-bung-13b.jpg
“The unit is trying to complete the installation of the remaining two spans by the end of June. Completing the entire construction will take some more time,” said engineer Hoang Minh Son, Commander of Hoa Binh 479 Joint Stock Company.
bqbht_br_cao-toc-vung-ang-bung-11a.jpg
bqbht_br_cao-toc-vung-ang-bung-2a.jpg
Due to the terrain and bridge project characteristics, work can only be carried out during the day, making it difficult to work overtime at night to ensure labor safety.
bqbht_br_cao-toc-vung-ang-bung-7.jpg
Meanwhile, the Deo But tunnel project undertaken by Son Hai Group is also being completed.
bqbht_br_cao-toc-vung-ang-bung-02.jpg
bqbht_br_cao-toc-vung-ang-bung-8.jpg
Up to now, the right tunnel has completed the concrete pavement, installation of mechanical and electrical systems, fire protection, and tunnel lining painting. The contractor committed to completing the construction of the right tunnel by the end of June.
bqbht_br_cao-toc-vung-ang-bung-01c.jpg
The Vung Ang - Bung expressway is 55.34 km long, passing through two provinces: Ha Tinh (12.9 km) and Quang Binh - now Quang Tri (42.44 km), with the starting point intersecting with National Highway 12C, connecting with Ham Nghi - Vung Ang expressway in Ky Tan commune, Ky Anh district, Ha Tinh province and the end point in Cu Nam commune, Bo Trach district, Quang Tri province, connecting with Bung - Van Ninh expressway.
bqbht_br_cao-toc-vung-ang-bung-12a.jpg
The project is invested by Project Management Board 6 (Ministry of Construction). The project is divided into 2 construction packages, of which, construction package XL01 is undertaken by Son Hai Group - Vietnam Construction and Import-Export Joint Stock Corporation - Joint Stock Company 484 - Joint Stock Company 369 - Joint Stock Company 479 Hoa Binh, while Phuong Thanh Transport Investment and Construction Joint Stock Company - Lizen Joint Stock Company undertakes construction package XL02. The section through Ha Tinh belongs to construction package XL01.
bqbht_br_cao-toc-vung-ang-bung-13.jpg
At the investment phase, the expressway has 4 lanes, no emergency lane, and a number of emergency stops are arranged every 4-5km with a roadbed width of 17m and a design speed of 60-90 km/h.
bqbht_br_cao-toc-vung-ang-bung-5.jpg
bqbht_br_cao-toc-vung-ang-bung-9.jpg
On the 12.9 km route through Ky Anh district and Ky Anh town, Ha Tinh province, except for bridge No. 1 constructed by Hoa Binh 479 Joint Stock Company, other items on the route have been basically completed.
bqbht_br_cao-toc-vung-ang-bung-5b.jpg
On many sections, contractors have painted road markings...
bqbht_br_cao-toc-vung-ang-bung-01.jpg
bqbht_br_cao-toc-vung-ang-bung.jpg
...installation of hard dividers, anti-glare nets, guardrails and traffic signs.
bqbht_br_cao-toc-vung-ang-bung-02b.jpg
According to plan, the Vung Ang - Bung expressway will be completed and put into operation on June 30.
ang-bung-vung-highway-02a.jpg
bqbht_br_cao-toc-vung-ang-bung-6.jpg
According to information from Project Management Board 6 (Ministry of Construction), up to now, the project's construction output has reached over 94% of the construction value, slower than the set plan. There are still some unfinished items on the route. The project site in the section passing through Quang Tri province (formerly Quang Binh) has not yet been 100% handed over.
bqbht_br_cao-toc-vung-ang-bung-01aa.jpg
Thus, the Vung Ang - Bung expressway cannot be opened and put into operation by the end of June 30 as planned by the Ministry of Construction.
Video: Vung Ang - Bung Expressway section through Ha Tinh.

Source: https://baohatinh.vn/cao-toc-vung-ang-bung-kho-ve-dich-vao-cuoi-thang-6-post290245.html


Comment (0)

No data
No data

Same tag

Same category

Braised Pig's Feet with Fake Dog Meat - A Special Dish of Northern People
Peaceful mornings on the S-shaped strip of land
Fireworks explode, tourism accelerates, Da Nang scores in summer 2025
Experience night squid fishing and starfish watching in Phu Quoc pearl island

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product