Speed ​​up the implementation of a series of transport projects worth 1 million billion VND

On May 10, Prime Minister Pham Minh Chinh, Head of the State Steering Committee for important national projects and works, key to the transport sector, chaired the 17th meeting.

Báo Tuổi TrẻBáo Tuổi Trẻ10/05/2025

cao tốc - Ảnh 1.

Prime Minister Pham Minh Chinh chairs the 17th meeting of the Steering Committee - Photo: VGP

The management projects under the Steering Committee include 37 projects/95 component projects, including 35 projects in the road sector and 2 projects in the aviation sector, with a total investment capital of over 1 million billion VND.

Up to now, 19 projects/component projects have been put into operation; 52 projects/component projects are under construction, basically following the set schedule.

Completed 2,268 km of highways

However, there is still a small area of ​​land, the relocation of technical infrastructure has not been completed, and the source of materials for the projects of Ring Road 3, Ho Chi Minh City, Chau Doc - Can Tho - Soc Trang is still not enough.

In the coming time, localities will resolutely implement the Lao Cai - Hanoi - Hai Phong railway project, ensuring conditions for construction to start at the end of 2025; and reconnecting the railway with China this May.

By 2025, the goal of putting 3,000 km of expressway into operation must be completed, the expressway from Cao Bang to Ca Mau must be opened, and 1,000 km of coastal road must be completed.

Regarding aviation, ensure the basic completion of the Long Thanh International Airport project in 2025. ACV and localities focus on completing airports: Expanding Noi Bai Terminal 2; Con Dao, Ca Mau, Chu Lai, Mang Den airports, Dong Hoi Airport Terminal 2...

In conclusion, Prime Minister Pham Minh Chinh once again emphasized the multifaceted importance of promoting transport infrastructure projects.

Up to now, the whole country has completed 2,268 km of expressway and is striving to complete another 800 km by the end of the year, achieving the goal of having at least 3,000 km of expressway.

Emphasize that the basic goals of the projects are unchanged, must ensure and accelerate progress, improve quality, not increase capital, not prolong, not corrupt, negative, wasteful, ensure safety, hygiene, and environment. In particular, the Cao Lanh - An Huu project must be inaugurated no later than December 19.

Continue to promote patriotism and responsibility to make more efforts and be more determined; continue to launch exciting patriotic emulation movements, arouse national pride, create an enthusiastic working atmosphere, with the highest sense of responsibility; promptly encourage, reward, propagate, mobilize people, create consensus and unanimity to implement projects.

cao tốc - Ảnh 2.

The Prime Minister assigned the State Bank to soon deploy a credit package of VND500,000 billion - Photo: VGP

Early implementation of 500,000 billion VND credit package

Accordingly, the Prime Minister requested to promote the highest sense of responsibility, mobilize the entire political system to speed up the progress and complete site clearance of projects. In particular, it is necessary to remove obstacles regarding construction materials in the Mekong Delta, complete procedures with mines, and meet the requirements of contractors, investors, and management boards.

Investors and contractors mobilize resources from local subcontractors, human resources, and machinery. For anything that can use manual labor, they mobilize military forces, police, and youth... The armed forces promote the heroic tradition and spirit of "forgetting oneself for the country, serving the people".

The Prime Minister directed that any arising issues must be handled immediately, and that the authority of each level must be handled, without shirking or avoiding. If the issue is beyond the authority, it must be reported to the competent authority for consideration and decision.

For public-private partnership projects, procedures should be quickly resolved. If there are any problems, the National Assembly should be proposed to use one law to amend many laws at the 9th session, promoting the implementation of projects in the spirit of Resolution 68 of the Politburo on private economic development.

The State Bank will soon deploy a VND500 trillion credit package for strategic infrastructure, science and technology, innovation, and digital transformation.

He requested that at the upcoming 18th meeting, there will be a review and proposal to reward groups and individuals who have done well, including rewarding projects with many technical improvements, helping to save costs, exceed progress, and improve quality; anyone with shortcomings must be pointed out, and anyone who fails to complete their tasks or commits violations must be promptly handled and disciplined.

Read more Back to Topics
NGOC AN

Source: https://tuoitre.vn/day-nhanh-trien-khai-loat-du-an-giao-thong-quy-mo-1-trieu-ti-dong-20250510141302552.htm


Comment (0)

No data
No data

Same category

Many beaches in Phan Thiet are covered with kites, impressing tourists.
Russian military parade: 'Absolutely cinematic' angles that left viewers stunned
Watch Russian fighter jets perform spectacularly at the 80th Anniversary of Victory Day
Cuc Phuong in butterfly season – when the old forest turns into a fairyland

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product