Identifying the disbursement of public investment capital as an important task, recently, Quang Ninh province has directed relevant departments, branches and localities to focus on removing difficulties and obstacles in administrative procedures, as well as implementing projects of enterprises and investors to speed up the disbursement of public investment capital in the area.
In the past 9 months, the disbursement of public investment capital in the province reached 5,794 billion VND, equal to 48.7% of the plan assigned at the beginning of the year, higher than the same period. In particular, the province has directed to accelerate the construction of projects: Riverside road connecting from Ha Long - Hai Phong expressway to Dong Trieu, section from Provincial Road 338 to Dong Trieu, section from Nha Mac lagoon intersection to Provincial Road 338; Renovation and upgrading of National Highway 279 section from Km0+00-Km8+600; Project to upgrade National Highway 4B section through Quang Ninh; Road connecting from Van Don - Mong Cai expressway to Van Ninh port... Simultaneously organized the groundbreaking, launching and inauguration of 51 key projects with a total investment of over 135 trillion VND on the occasion of the 80th anniversary of the August Revolution and National Day September 2.
Determined to complete the 2025 public investment disbursement plan, provincial leaders directly inspected many projects being implemented in the area, especially increasing unannounced, surprise inspections to promptly grasp the progress and difficulties of the projects.

Recently, after inspecting the construction organization and directing the resolution of a number of difficulties and problems to speed up the progress of the National Highway 279 Renovation and Upgrade Project, Mr. Bui Van Khang, Chairman of the Provincial People's Committee, requested the investor and contractors to closely coordinate with relevant departments, branches and localities to promptly resolve the difficulties and problems; continue to increase human resources and equipment, take advantage of favorable weather, and continuously work in 3 shifts and 4 teams to speed up the construction progress. Quang Hanh Ward authorities and related units approved the land clearance plan for households and organizations, determined to complete the site clearance in November 2025.
For sections that are eligible for graded construction, it is necessary to implement immediately to increase the disbursement volume, contributing to the overall growth of the province in 2025. In particular, the last 2km section of the route will be completed in 2025. For other items, it is necessary to urgently complete before June 2026 to put into operation, promoting post-investment efficiency.
With the close and drastic direction of the provincial leaders, Quang Ninh has also promptly adjusted and supplemented the medium-term public investment plan for the period 2021-2025 with provincial budget capital. Therein, capital is reduced from projects that are still facing difficulties in construction implementation to projects with favorable construction and implementation conditions.
As at the 32nd Session, the 14th Provincial People's Council passed Resolution 307/2025/NQ-HDND on adjusting and supplementing the medium-term public investment plan for the 2021-2025 period with provincial budget capital. In particular, the adjustment reduced 3,120 billion VND of 2 projects: Riverside road connecting from Ha Long - Hai Phong expressway to Dong Trieu, section from Provincial Road 338 to Dong Trieu, phase 1 (sub-project 2: Construction part): 2,370 billion VND; Project to improve and upgrade Road 342 section in Ky Thuong commune, Quang Ninh province: 750 billion VND.
At the same time, supplement the capital portfolio and plan in the medium-term plan from the adjusted reduction of 3,120 billion VND. Of which, supplement the capital portfolio and plan in the medium-term plan for the Quang Ninh Provincial Farmers Support Fund and 7 newly started projects: 820 billion VND. Allocate the capital plan according to the norm for 54 communes, wards, and special zones to invest in construction, upgrade, and expansion of traffic infrastructure, drainage, urban and residential area renovation; renovation, investment, and upgrading of cultural institutions: 2,300 billion VND.
The provincial leaders have strengthened the inspection of projects, along with Quang Ninh province urgently adjusting and supplementing public investment capital, showing the determination and closeness in the direction and management of the province. Quang Ninh also determined that the completion of public investment capital disbursement is a measure of the operational efficiency of departments, branches, sectors and commune-level authorities. Therefore, with the remaining period of 2025 not being long, it requires more determination, flexibility and closeness in disbursing public investment capital from units and localities.
Source: https://baoquangninh.vn/dieu-chinh-von-day-nhanh-giai-ngan-dau-tu-cong-3381331.html