The installation of transformer T2, located within the premises of the 110kV Nam Sach 2 substation, commenced on September 30th. The main objective of the project is to ensure a safe and stable power supply to loads in the An Phat 1 and An Phat 2 industrial zones and surrounding areas.
The commissioning of transformer T2 not only helps prevent overloading of transformer T1, but also reduces the load on nearby 110kV substations, improving the reliability of power supply and reducing power losses for the medium-voltage grid throughout the region.
The entire system is designed to modern standards, integrating remote data collection, monitoring, and control technology, directly connected to the Hai Phong Remote Control Center, fully meeting the criteria for operating unmanned substations.
The project is invested by Hai Phong Power Company with a total cost of over 31.4 billion VND.
HUYEN TRANGSource: https://baohaiphong.vn/dong-dien-may-bien-ap-t2-tai-tram-bien-ap-110kv-nam-sach-2-529776.html