The route will have a total length of about 32.3 km, starting from Con Thoi commune, Kim Son district (intersecting with the coastal road), passing through Kim Son, Yen Mo, Nho Quan districts, Tam Diep city (Ninh Binh), and ending at Dong Giao intersection - the connection point with Ho Chi Minh road in Hoa Binh province.
![]() |
Tam Diep City will be the final point of the inter-regional connecting road project. Photo: TB |
The project aims to connect key national traffic routes, such as: North-South Expressway in the East; National Highway 1, National Highway 12B, National Highway 45, National Highway 10; coastal roads through the coastal plain provinces of the North and North Central regions; Ho Chi Minh Road connecting the Northwest region.
Thereby, the project will create momentum to promote the development of economic linkages between the lowlands and the highlands, expanding development space for Thanh Hoa, Ninh Binh, Hoa Binh provinces and neighboring areas.
The project is divided into two types of investment. Normal section (26.3 km): Construction of a 37 m wide main road, including 4 motor lanes, 2 mixed lanes, and a 15 m wide reserve strip in the middle (average clearance of 50 m). Section through densely populated areas (2.5 km): Larger scale with road surface B = 61 m, with collector roads on both sides, the reserve strip in the middle remains at 15 m. Clearance of the land according to the complete scale B = 70 m to facilitate future expansion.
The project has a total estimated investment of nearly 6,940 billion VND, mobilized from the Ninh Binh provincial budget, allocated according to the medium-term public investment plan for the 2021-2025 and 2026-030 periods. Project implementation period: from 2025 to 2028. The project is invested by the Ninh Binh Provincial Traffic Construction Investment Project Management Board.
Previously, the project with the largest total investment in the province was the East-West Ninh Binh route with an investment capital of VND2,000 billion. The implementation of this new inter-regional route demonstrates the province's determination to make a breakthrough in transport infrastructure, creating a strong shift in attracting investment and developing the regional economy.