For Component 1 Project, the district has handed over more than 67.6 hectares of land to the Provincial Traffic Construction Investment Project Management Board for construction, reaching 86.5% of the land area to be recovered. For Component 2 Project, the district has handed over 145.6 hectares of land to Project 85 Management Board for construction, reaching 86.5% of the land area to be recovered.
Regarding the relocation of technical infrastructure (electricity, water, telecommunications, etc.) out of the highway boundary, the District People's Committee has approved the design and construction drawings for Component 1 and the budget for 2025 and is organizing the relocation. The District People's Committee has also approved the design and construction drawings for Component 2 and the budget for 2024 and is organizing the relocation.