The implementation value of Component Project 1, Cao Lanh - An Huu Expressway reached 16.3%.
The project started on June 25, 2023 and is expected to be completed in October 2025.
Regarding the progress of the Cao Lanh - An Huu Expressway Project, Phase 1, Component 1, the People's Committee of Dong Thap province said that regarding site clearance, the compensation plan for 101.14 hectares has been approved, and the site has been handed over for 100.78 hectares, reaching 99.63%.
Up to now, 7/16 bid packages have been completed; contractor selection has been completed, contracts have been signed and contracts are being implemented for 7/16 bid packages; and contractors are being prepared for 2/16 bid packages (Consulting on construction standards and Consulting on construction quality inspection).
Construction of Cao Lanh - An Huu Expressway, phase 1. |
Currently, the contractor is implementing the road construction: sand filling to restore the main route reaching 1/14.6 km, sand filling to restore the public road reaching 8.3/20.3 km; continuous floor beam section: prestressed concrete pile driving 1,002/1,157 center. For the bridge section, construction is organized at 16/19 bridges, launching 4-span beams. The implementation value is 414.1/2,540 billion VND, reaching 16.3%.
The Cao Lanh - An Huu Expressway Construction Project, Phase 1, has a length of about 27.43 km, divided into 2 component projects. Component project 1 (Km0+000 - Km16+000) is about 16 km long in Dong Thap province, with a preliminary total investment of about 3,640 billion VND, implemented by the People's Committee of Dong Thap province. The project started on June 25, 2023, and is expected to be completed in October 2025.
Component project 2 (Km16+000 - Km27+430) is about 11.43 km long in Dong Thap and Tien Giang provinces, with a preliminary total investment of about 3,856 billion VND, implemented by the People's Committee of Tien Giang province.