Implementation value of Component Project 1, Cao Lanh Expressway

Báo Đầu tưBáo Đầu tư30/03/2024


The implementation value of Component Project 1, Cao Lanh - An Huu Expressway reached 16.3%.

The project started on June 25, 2023 and is expected to be completed in October 2025.

Regarding the progress of the Cao Lanh - An Huu Expressway Project, Phase 1, Component Project 1, Dong Thap Provincial People's Committee said that regarding site clearance, the compensation plan for 101.14 hectares has been approved, and the site has been handed over for 100.78 hectares, reaching 99.63%.

Up to now, 7/16 bid packages have been completed; contractor selection, contract signing and implementation of 7/16 bid packages are being completed; and contractors are being prepared for 2/16 bid packages (Consulting on construction standards and Consulting on construction quality inspection).

Construction of Cao Lanh - An Huu Expressway, phase 1.

Currently, the contractor is implementing the road construction: sand filling to restore the main route reaching 1/14.6 km, sand filling to restore the public road reaching 8.3/20.3 km; continuous floor beam section: prestressed concrete pile driving 1,002/1,157 center. For the bridge section, construction is organized at 16/19 bridges, launching 4-span beams. The implementation value is 414.1/2,540 billion VND, reaching 16.3%.

The Cao Lanh - An Huu Expressway Construction Project, Phase 1, is approximately 27.43 km long and is divided into two component projects. Component Project 1 (Km0+000 - Km16+000) is approximately 16 km long and is located in Dong Thap province, with a preliminary total investment of approximately VND 3,640 billion, implemented by the Dong Thap Provincial People's Committee. The project started on June 25, 2023 and is expected to be completed in October 2025.

Component project 2 (Km16+000 - Km27+430) is about 11.43 km long in Dong Thap and Tien Giang provinces, with a preliminary total investment of about 3,856 billion VND, implemented by the People's Committee of Tien Giang province.



Source

Comment (0)

No data
No data
Wild beauty on Ha Lang grass hill - Cao Bang
Vietnam Air Force practices preparing for A80
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product