Vietnam.vn - Nền tảng quảng bá Việt Nam

The shape of the flyover is expected to eliminate the "black spot" of traffic congestion at the gateway to Hanoi before the opening day.

Báo Dân ViệtBáo Dân Việt05/03/2024


The shape of the flyover is expected to eliminate the "black spot" of traffic congestion at the gateway to Hanoi before the opening day.

Tuesday, March 5, 2024 1:29 PM (GMT+7)

After more than 1 year of construction, the project to build two urban overpasses at Mai Dich intersection (Cau Giay district, Hanoi) has taken shape, currently reaching over 80% of the construction volume. The project is expected to be completed and open to traffic before March 31, 2024.

Video : Urban overpass at Mai Dich intersection, Cau Giay district, Hanoi before opening to traffic.

Hình hài cầu vượt được kỳ vọng xóa

The project to build two urban bridge units and organize traffic at Mai Dich intersection (Cau Giay district, Hanoi) is being implemented over a length of about 760 m. The starting point of the project is on Pham Van Dong street (km19+000), the ending point is on Pham Hung street (km19+700, according to the route of Ring Road 3). In the photo, the red lines are the shapes of two urban overpasses.

Hình hài cầu vượt được kỳ vọng xóa

The project started on February 14, 2023 and was targeted to be completed in 2023. However, due to land acquisition and investment procedures, the project could not be implemented on site until May 2023. Therefore, the completion date has been pushed back to the first quarter of 2024.

Hình hài cầu vượt được kỳ vọng xóa

In the photo, two urban overpasses run parallel to the Mai Dich overpass, above is the Nhon - Hanoi railway station elevated railway line.

Hình hài cầu vượt được kỳ vọng xóa

According to Dan Viet reporters on the morning of March 5, the project to build two urban overpasses at Mai Dich intersection (Cau Giay district, Hanoi) has completed the main items.

Hình hài cầu vượt được kỳ vọng xóa

Currently, the contractor is urgently completing the final tasks such as installing the bridge railing system, asphalt bridge surface, and lighting system.

Hình hài cầu vượt được kỳ vọng xóa

At both ends of the bridge, machinery and workers are constructing some remaining items of the approach road.

Hình hài cầu vượt được kỳ vọng xóa

The investor representative said that the project has now reached over 80% of its volume. The contractor is mobilizing a large number of workers to construct the project, completing the project before March 31, 2024.

Hình hài cầu vượt được kỳ vọng xóa

The contractor is currently speeding up progress to finish before March 31, 2024.

Hình hài cầu vượt được kỳ vọng xóa

The construction of two urban overpasses over the past year has made it difficult for vehicles to move. Specifically, trucks and inter-provincial passenger buses that want to go straight from Pham Hung Street to Pham Van Dong Street are not allowed to move under the Mai Dich overpass, they are only allowed to move on the Mai Dich overpass to reduce congestion at the Mai Dich - Pham Van Dong intersection.

Hình hài cầu vượt được kỳ vọng xóa

Traffic reorganization has caused the road leading to Mai Dich overpass to be frequently congested even during non-rush hours.

Hình hài cầu vượt được kỳ vọng xóa

The project is expected to increase traffic capacity at Mai Dich intersection, contributing to solving traffic congestion in the northern area of ​​Hanoi.

Pham Hung



Source

Comment (0)

No data
No data

Same tag

Same category

Wildlife on Cat Ba Island
The fiery red sunrise scene at Ngu Chi Son
10,000 antiques take you back to old Saigon
The place where Uncle Ho read the Declaration of Independence

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product