Long Thanh airport resettlement area, need to quickly build both school and market

VietNamNetVietNamNet09/09/2023


On the morning of September 9, Mr. Vu Hong Thanh, Chairman of the National Assembly's Economic Committee, led a working delegation of the Standing Committee of the Economic Committee to inspect and supervise the implementation of the National Assembly's Resolutions on socio-economic issues and important national projects in the field of transport in Dong Nai province.

The working group inspected the actual situation at Long Thanh airport. Photo: Hoang Anh

The working group conducted a field survey at the Long Thanh International Airport construction site project (Long Thanh airport), Loc An - Binh Son resettlement area, Bien Hoa - Vung Tau expressway project, T1 road connecting Long Thanh airport, Long Duc resettlement area (Bien Hoa - Vung Tau expressway resettlement area).

Reporting to the working group, a representative of the Vietnam Airports Corporation (ACV) said that the terminal, runway, and apron projects have just started. The entire site for the project has been handed over by the locality since August 25.

The delegation then went to the Loc An - Binh Son resettlement area (Loc An commune, Long Thanh district), and visited some construction sites for schools and markets.

A school project in the Loc An - Binh Son resettlement area is nearing completion. Photo: Hoang Anh

Mr. Le Anh Tuan, Deputy Minister of Transport, said that at schools under construction, it is necessary to plant many large trees to create shade for students when they go to school.

Here, Mr. Vu Hong Thanh, Chairman of the National Assembly 's Economic Committee, requested that construction units speed up the school construction progress so that students can soon have a new, spacious school.

"Schools must be built quickly so students can go to school, and markets must be completed quickly so people can shop more easily," said Mr. Vu Hong Thanh.

The working group of the Standing Committee of the Economic Committee continued to survey the Bien Hoa - Vung Tau Expressway project, at the construction site, it was noted that some construction machinery was working at a slow pace. The delegates requested the functional units to speed up site clearance to serve the project's construction progress.

At the Long Duc resettlement area (Long Duc commune, Long Thanh district), the working group conducted a field survey and checked the project progress. However, the field survey recorded that the resettlement area still had many messy items.

Mr. Vu Hong Thanh said that the resettlement area should be completed so that people have a new place to live before handing over the land. The locality should ask for a mechanism to increase human resources to support large projects to speed up the project progress.

Reporting to the working delegation, Mr. Vo Tan Duc, acting Chairman of Dong Nai Provincial People's Committee, said that the locality has a temporary resettlement policy for people whose land has been recovered to serve projects.

“If there is no resettlement land, the locality will support people temporarily for 5 months, 3 million VND per month. After 5 months, if there is still no resettlement, the temporary residence will be extended. Many Dong Nai projects started a bit late but the acceleration and finishing stages are fast,” said Mr. Duc.

Regarding human resources, Mr. Duc said that recently, Dong Nai mobilized officials from departments and localities without projects to support the Bien Hoa - Vung Tau expressway and Ring Road 3 - Ho Chi Minh City.

In addition, Dong Nai also established a separate Compensation and Site Clearance Board to serve the projects.



Source

Comment (0)

No data
No data

Same tag

Same category

What's interesting in Da Nang this summer?
Wildlife on Cat Ba Island
Enduring journey on the rocky plateau
Cat Ba - Symphony of Summer

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product